File #: 970019    Version: 0 Name: Masonry Repair- Fire Station Two Drill Tower (Waiver of Bids Requested
Type: Contract/Request Status: Passed
File created: 8/4/1997 In control: Village Board
On agenda: Final action: 3/1/2016
Title: VILLAGE OF LOMBARD REQUEST FOR BOARD OF TRUSTEES ACTION For Inclusion on Board Agenda BIDS AND PROPOSALS President and Village Board of Trustees
Indexes: Contract, Fire, King
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

 

        VILLAGE OF LOMBARD

REQUEST FOR BOARD OF TRUSTEES ACTION

    For Inclusion on Board Agenda

         BIDS AND PROPOSALS

President and Village Board of Trustees

body

 

TO              President and Village Board of Trustees

FROM            William T. Lichter, Village Manager

 

 

DATE

 

 

 

 August 5, 1997          Agenda Date: August 14, 1997

 

 

 

Bid Opening For:      Masonry Repair-Drill Tower-F.S. 2

 

 

 

TITLE            Bid Opening For: Masonry Repair- F.S. 2 Tower

 

SUBMITTED  BY:     George E. Seagraves, Fire Chief

 

RESULTS:

 

Date Bids Were Published                 Date Bidding Closed

Total Number of Bids Received

Total Number of Bidders Meeting Specifications

 

 

 

Bid Security Required                 Yes                    No

Performance Bond Required             Yes                    No

Were Any Bids Withdrawn               Yes                    No

  Explanation:

Waiver of Bids Requested?        x    Yes                    No

  If yes, explain:

       See below and attached memorandum.

Award Recommended to Lowest           Yes                    No

  Responsible Bidder?

 

 

 

If no, explain:

 

FISCAL IMPACT:

 

Engineer's estimate/budget estimate $9,800.00

Amount of Award     $18,460.00

 

 

 

BACKGROUND/RECOMMENDATION:,

 

        Work exceeded original estimate after quotes were received.  Due to time

        considerations, and cost savings, waiver of bid is requested.

 

 

 

Has Recommended Bidder Worked for Village Previously _     Yes X   No

If yes, was quality of work acceptable                     Yes     No

Was item bid in accordance with Public Act 85-1295?        Yes     No

Waiver of bids - Public Act 85-1295 does not apply     x   Yes

 

 

 

REVIEW (as needed):

Village Attorney XX                                       Date

Finance Director XX                                       Date

Village Manager XX                                        Date

 

NOTE: All materials must be submitted to and approved    by the Village

Manager's Office by 12:00 Noon, Wednesday, prior to the Board Agenda

distribution.

 

 

 

 

MEMORANDUM

 

TO:                                          William T. Lichter, Village Manager

                                          

FROM:                             George E. Seagraves, Fire Chief

 

DATE:                                          August 4, 1997

 

RE:                                          BID WAIVER/MASONRY FIRE STATION 2 TOWER

 

I request permission to waive bidding and award a contract to Brian King Masonry, Inc.,

of Villa Park, Illinois, in the amount of $18,400.00.  This will encompass the repair of

brick and block on the drill tower located at Fire Station 2.

 

Originally, the engineer for the project, Wiss, Janney and Elstner, thought masonry work

would be less than $10,000.00, and the engineering costs to do complete specifications

for this type of work was unnecessary.  However, during site inspections by the Masons,

it was discovered that more brick needs to be removed than estimated by the engineers.  

 

Four masons were contracted and two returned quotes.  Brian King Masonry was the

lowest quote at $18,400.00; and Du-Cook of Bensenville, Illinois, was $18,917.00.  Du-

Cook was the low quote for the ground sign, and a purchase order will be given to them

for this work in the amount of $3,866.00.

 

Our engineering firm reviewed the additional work and finds the quotes to be in order

and appropriate for the work.

 

It has taken two plus months to get quotes.  Masons of any respect are busy and I believe

it would be difficult to get bidders for such a small job.  The bids also would not give us

any better prices, but would increase our engineering costs.  I am also concerned that we

could run into weather issues, if we delay the project to bid.  The main part of the

restoration project is the masonry and it should be done first. 

 

We have budgeted $45,000.00 for the entire project and the Fire Department is acting as

the general for the project.  Our project to renovate the drill tower is as follows:

 

 

 

 

 

 

PHASE I

 

Masonry (quote)                                                                                                         $    18,400.00

Replace stairs (engineer)                                                                     7,800.00

Steel shoring second floor (engineer)                                                1,200.00

Asphalt roof tower (engineer)                                                                     3,000.00                                                                                          

Replace down spout (fire department)                                     150.00

New main doors (quote)                                                                             1,730.00

Remove electric (fire department)                                                  200.00

 

Sub Total Phase 1                                                                                                                              $  32,480.00

 

PHASE II

 

Replace shingle roof (fire department)                              $    4,600.00

Ladder stand offs (fire department)                                                  900.00

New hatch cover (engineer)                                                                     1,200.00

Seal brick/concrete block (fire department)                           4,000.00

 

Sub Total Phase II                                                                                                                              $  10,700.00

 

PHASE III

 

Window frames (fire department)                                                               $     4,500.00

Electrical (fire department)                                                                     3,500.00

 

Sub Total Phase III                                                                                                                              $   8,000.00

 

Grand Total                                                                                                                                                    $  51,180.00                                          

 

The project is phased to insure the most critical items are completed first.  If required,

additional funds will be requested in fiscal year 1999, to complete the entire project.

 

Respectfully,

 