File #: 980523    Version: 0 Name: Change Order No. 1 Olde Towne Phase III (Resolution)
Type: Resolution Status: Passed
File created: 9/3/1998 In control: Village Board
On agenda: Final action: 9/17/1998
Title: R E S O L U T I O N R_______________99 A RESOLUTION AUTHORIZING A CHANGE ORDER INVOLVING A DECREASE IN THE DOLLAR AMOUNT OF THE CONTRACT OF $10,000 OR MORE
Indexes: Change Order, Olde Towne, Szabo
title
R E S O L U T I O N
R_______________99

A RESOLUTION AUTHORIZING A CHANGE ORDER
INVOLVING A DECREASE IN THE DOLLAR AMOUNT OF
THE CONTRACT OF $10,000 OR MORE

body

WHEREAS, pursuant to Illinois Compiled Statutes, Chapter 720, Section 5/33E-9, units of local government are required to make specific findings prior to authorizing any change order relative to a contract which would increase or decrease the dollar amount of the contract by $10,000 or more, or would extend or shorten the time in which the contract is to be completed by thirty days or more; and

WHEREAS, staff has presented and recommended the proposed Change Order No. 1 to the contract between the Village of Lombard and the Szabo Contracting, Inc. regarding the Olde Towne Improvements, Phase III project as attached hereto as Exhibit "A" and made part hereof, to the Corporate Authorities of the Village of Lombard; and

WHEREAS, said change order attached hereto as Exhibit "A" would increase the dollar amount of the contract by $22,409.12.

NOW, THEREFORE, BE IT RESOLVED BY THE PRESIDENT AND BOARD OF TRUSTEES OF THE VILLAGE OF LOMBARD, DU PAGE COUNTY, ILLINOIS, as follows:

SECTION 1: That after reviewing the explanation of staff as to the necessity of and reasons for the change order attached hereto as Exhibit "A", the President and Board of Trustees find as follows:

A That the circumstances which necessitated said change order were not reasonably foreseeable at the time the contract was entered into.

B. That the basis of the change order was not within the contemplation of the contract when the contract was signed.

C. That it is in the best interests of the Village of Lombard to approve the change order in its proposed form.

D. That to the extent that it may have been necessary to go to bid relative to the work contemplated by said change order, bidding is hereby specifically waived as to the change order work.

SECTION 2: That having made the findings s...