File #: 130631    Version: 1 Name: 2013 Driveway Apron, Curb and Sidewalk Restoration Program, Final Balancing Change Order No. 2
Type: Resolution Status: Passed
File created: 12/5/2013 In control: Village Board of Trustees
On agenda: Final action: 12/19/2013
Title: 2013 Driveway Apron, Curb and Sidewalk Restoration Program, Final Balancing Change Order No. 2 Reflecting a decrease to the contract with Kings Point General Cement in the amount of $92,198.05. (DISTRICTS - ALL)
Attachments: 1. 130631 BOT 12-19-13, 2. R 177-13.pdf, 3. Change Order 2.130631.pdf, 4. Cover Sheet 130631.pdf
Title
2013 Driveway Apron, Curb and Sidewalk Restoration Program, Final Balancing Change Order No. 2
Reflecting a decrease to the contract with Kings Point General Cement in the amount of $92,198.05.  (DISTRICTS - ALL)