File #: 110425    Version: 0 Name: North Industrial Park Pavement Rehabilitation Final Balancing Change Order No. 4
Type: Resolution Status: Passed
File created: 6/28/2011 In control: Village Board of Trustees
On agenda: Final action: 8/18/2011
Title: North Industrial Park Pavement Rehabilitation Final Balancing Change Order No. 4 Authorizing a decrease in the amount of $228,399.54 to the contract with Plote Construction. (DISTRICTS #1 & #4)
Attachments: 1. R 17-12.pdf, 2. 110425BOT8-18-11.pdf, 3. Change Order 4 Plote Construction.pdf
Title
North Industrial Park Pavement Rehabilitation Final Balancing Change Order No. 4
Authorizing a decrease in the amount of $228,399.54 to the contract with Plote Construction.  (DISTRICTS #1 & #4)