File #: 110090    Version: 0 Name: 2010 North Avenue Standpipe Exterior Painting Project, Additional Work Request, Change Order No. 1 - Final
Type: Resolution Status: Passed
File created: 3/3/2011 In control: Village Board of Trustees
On agenda: Final action: 3/23/2011
Title: 2010 North Avenue Standpipe Exterior Painting Project Additional Work Request, Change Order No. 1 - Final Authorizing a decrease to the contract with Tecorp, Inc. in the amount of $44,825.00 due to the project being halted when additional corrosion was found on the roof that was beyond the scope of the project. (DISTRICT #1)
Attachments: 1. 110090 BOT.pdf, 2. R 83-11.pdf, 3. Change Order 1 Final Tecorp WA 10-02B.pdf
Title
2010 North Avenue Standpipe Exterior Painting Project Additional Work Request, Change Order No. 1 - Final
Authorizing a decrease to the contract with Tecorp, Inc. in the amount of $44,825.00 due to the project being halted when additional corrosion was found on the roof that was beyond the scope of the project.  (DISTRICT #1)