Title:
|
FY2023 Concrete Rehabilitation Program, Change Order #1
Reflecting an increase to the contract with G & M Cement Construction, Inc. in the amount of $27,750.00. This increase is needed to adjust the contract quantities to reflect the addition of 1,200 #6 dowel bars used throughout the Village and added traffic control to facilitate the road closures required on Highland Ave. (DISTRICTS - ALL)
|