File #: 050275    Version: 0 Name: FY2005 Driveway Apron and Sidewalk Restoration Change Order No. 2 - Final Balancing
Type: Resolution Status: Passed
File created: 5/11/2005 In control: Village Board
On agenda: Final action: 6/2/2005
Title: P. Change Order No. 2 (Final Balancing) - FY 2005 Driveway Apron and Sidewalk Restoration Program (Resolution) Resolution authorizing final balancing Change Order No. 2 to the contract with Leahy Construction Company, Inc. reflecting an increase of $13.60 for work associated with the FY 05 Driveway Apron and Sidewalk Replacement Program.
Indexes: Change Order
Attachments: 1. 050275.pdf
Title
P.   Change Order No. 2 (Final Balancing) - FY 2005 Driveway Apron and Sidewalk Restoration Program (Resolution)
Resolution authorizing final balancing Change Order No. 2 to the contract with Leahy Construction Company, Inc. reflecting an increase of $13.60 for work associated with the FY 05 Driveway Apron and Sidewalk Replacement Program.
Body
[Enter body here.]