File #: 120279    Version: 1 Name: FY2012 Sewer Televising and Cleaning Program, Final Balancing Change Order No. 3
Type: Resolution Status: Passed
File created: 5/11/2012 In control: Village Board of Trustees
On agenda: Final action: 6/21/2012
Title: FY2012 Sewer Televising and Cleaning Program, Final Balancing Change Order No. 3 Reflecting a decrease to the contract with Pirtano Construction Company in the amount of $18,945.58.
Attachments: 1. 120279 PWC 6-12-12, 2. 120279 BOT 6-21-12, 3. 120279Coverpage6-21-12, 4. R 13-13, 5. Change Order 3 Pirtano, 6. PO #068102 PIRTANO CO#3.pdf, 7. PO #068102 Pirtano CO.pdf
Title
FY2012 Sewer Televising and Cleaning Program, Final Balancing Change Order No. 3
Reflecting a decrease to the contract with Pirtano Construction Company in the amount of $18,945.58.
Body
[Enter body here.]