File #: 110091    Version: 0 Name: 2010 North Avenue Standpipe Exterior Painting Project, Change Order No. 1 - Final
Type: Resolution Status: Passed
File created: 3/3/2011 In control: Village Board of Trustees
On agenda: Final action: 3/23/2011
Title: 2010 North Avenue Standpipe Exterior Painting Project, Change Order No. 1 - Final Authorizing a decrease to the contract with Tecorp, Inc. in the amount of $16,058.24, and also decreasing the contract time by 125 days due to the stoppage of work when significant corrosion was found on the roof of the North Avenue Standpipe. (DISTRICT #1)
Attachments: 1. 110091 BOT.pdf, 2. R 84-11.pdf, 3. Change Order 1 final Tecorp.pdf
Title
2010 North Avenue Standpipe Exterior Painting Project, Change Order No. 1 - Final
Authorizing a decrease to the contract with Tecorp, Inc. in the amount of $16,058.24, and also decreasing the contract time by 125 days due to the stoppage of work when significant corrosion was found on the roof of the North Avenue Standpipe.  (DISTRICT #1)