File #: 150510    Version: 1 Name: FY2015 Concrete Rehabilitation and Utility Cuts Patching, Final Balancing Change Order No. 2
Type: Resolution Status: Passed
File created: 10/29/2015 In control: Village Board of Trustees
On agenda: Final action: 11/19/2015
Title: FY2015 Concrete Rehabilitation and Utility Cuts Patching, Final Balancing Change Order No. 2 Reflecting an increase to the contract with G&M Cement Construction in the amount of $23,647.94. (DISTRICTS - ALL)
Attachments: 1. 150510 BOT 11-19-15, 2. R 78-15, 3. Cover Page 150510

Title

FY2015 Concrete Rehabilitation and Utility Cuts Patching, Final Balancing Change Order No. 2

Reflecting an increase to the contract with G&M Cement Construction in the amount of $23,647.94.  (DISTRICTS - ALL)

Body

[Enter body here.]