File #: 050547    Version: 0 Name: Yorktown Watermain Change Order No. 3 (Resolution)
Type: Resolution Status: Passed
File created: 9/30/2005 In control: Village Board
On agenda: Final action: 10/6/2005
Title: *S. 2004 Yorktown Watermain Change Order #3 (Resolution) Resolution authorizing Change Order No. 3 to the contract with Trine Construction Company reflecting an increase of $42,197.34 for work associated with the Yorktown Watermain project. (DISTRICT #3)
Indexes: Change Order, Trine, Watermain, Yorktown
Attachments: 1. 050547.pdf
Title
*S.  2004 Yorktown Watermain Change Order #3 (Resolution)
Resolution authorizing Change Order No. 3 to the contract with Trine Construction Company reflecting an increase of $42,197.34 for work associated with the Yorktown Watermain project.  (DISTRICT #3)
Body
[Enter body here.]