File #: 230328    Version: 1 Name: 22nd Street Junction Chamber, Change Order #1
Type: Resolution Status: Passed
File created: 9/29/2023 In control: Village Board of Trustees
On agenda: Final action: 10/19/2023
Title: 22nd Street Junction Chamber, Change Order #1 Reflecting an increase to the contract with John Neri Construction Company in the amount of $11,500.00. The revised contract amount represents the cost increase associated with installing a pressure connection on the 22nd Street sanitary sewer force main. (DISTRICT #3)
Attachments: 1. 230328 Board Meeting Attachment 10.19.23, 2. John Neri 22nd Street Junction Chamber Changer Order 1.pdf, 3. R 53-23.pdf, 4. Cover Page - 230328.pdf

Title

22nd Street Junction Chamber, Change Order #1

Reflecting an increase to the contract with John Neri Construction Company in the amount of $11,500.00. The revised contract amount represents the cost increase associated with installing a pressure connection on the 22nd Street sanitary sewer force main. (DISTRICT #3)

Body

[Enter body here.]