Title
Finley Road Pavement Rehabilitation, Phase 1, Final Balancing Change Order No. 4
Resolution reflecting an increase to the contract with "D" Construction in the amount of $39,743.24 due to major dollar items for time and material billings related to difficulties, conflicts and delays encountered during the construction of the underground utility improvements. (DISTRICTS #1, #2 & #6)