File #: 130360    Version: 1 Name: Finley Road Pavement Rehabilitation, Phase 1, Final Balancing Change Order No. 4
Type: Resolution Status: On Consent Agenda
File created: 7/26/2013 In control: Village Board of Trustees
On agenda: Final action: 8/15/2013
Title: Finley Road Pavement Rehabilitation, Phase 1, Final Balancing Change Order No. 4 Resolution reflecting an increase to the contract with "D" Construction in the amount of $39,743.24 due to major dollar items for time and material billings related to difficulties, conflicts and delays encountered during the construction of the underground utility improvements. (DISTRICTS #1, #2 & #6)
Attachments: 1. 130360 BOT 8-15-13, 2. R 124-13.pdf, 3. 130360 Cover Page.pdf, 4. CO #4 (Final) D Construction.pdf
Title
Finley Road Pavement Rehabilitation, Phase 1, Final Balancing Change Order No. 4
Resolution reflecting an increase to the contract with "D" Construction in the amount of $39,743.24 due to major dollar items for time and material billings related to difficulties, conflicts and delays encountered during the construction of the underground utility improvements.  (DISTRICTS #1, #2 & #6)