| 1 | | DuPage County and Village of Lombard Stormwater Ordinances | Ordinance | DuPage County and Village of Lombard Stormwater Ordinances
Recommendations to adopt the current version of DuPage Countywide Stormwater and Floodplain ordinance and DuPage County's General Certificates for Permitting, and to amend Village Code 151.55 to lower the threshold for stormwater detention to 5,000 square feet. Waiver of first reading is requested by to accomodate permitting for pending development. (DISTRICTS - ALL) | Recommended to the Board of Trustees with condition(s) | Pass |
Action details
|
Not available
|
120253
| 1 | | FY2012 Cracksealing Program, Final Balancing Change Order No. 2 | Resolution | FY2012 Cracksealing Program, Final Balancing Change Order No. 2
Reflecting a decrease to the contract with SKC Construction in the amount of $2,339.96. | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
120270
| 1 | | FY2012 Concrete Rehabilitation & Utility Cuts, Final Balancing Change Order No. 2 | Resolution | FY2012 Concrete Rehabilitation & Utility Cuts, Final Balancing Change Order No. 2
Reflecting a decrease to the contract with G&M Cement Construction in the amount of $1,129.42. | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
120278
| 1 | | FY2012 Concrete Driveway, Apron and Sidewalk Restoration, Final Balancing Change Order No. 3 | Resolution | FY2012 Concrete Driveway, Apron and Sidewalk Restoration, Final Balancing Change Order No. 3
Reflecting a decrease to the contract with Strada Construction, Inc. in the amount of $1,010.65. | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
120279
| 1 | | FY2012 Sewer Televising and Cleaning Program, Final Balancing Change Order No. 3 | Resolution | FY2012 Sewer Televising and Cleaning Program, Final Balancing Change Order No. 3
Reflecting a decrease to the contract with Pirtano Construction Company in the amount of $18,945.58. | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
120283
| 1 | | FY2012B Concrete Rehabilitation & Utility Cuts Patching, Change Order No. 1 | Resolution | FY2012B Concrete Rehabilitation & Utility Cuts Patching, Change Order No. 1
Reflecting an increase to the contract with G&M Cement Construction in the amount of $130,870.00. (DISTRICTS - ALL) | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
120284
| 1 | | FY2012B Driveway Apron, Curb & Sidewalk Restoration Program, Change Order No. 1 | Resolution | FY2012B Driveway Apron, Curb & Sidewalk Restoration Program, Change Order No. 1
Reflecting an increase to the contract with Kings Point General Cement, Inc. in the amount of $57,028.00. | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
120327
| 1 | | Lift Station Improvements, Ph 1, Final Balancing Change Order No. 2 | Resolution | Lift Station Improvements, Phase 1, Final Balancing Change Order No. 2
Reflecting an increase to the contract with Thorne Electric, Inc. in the amount of $9,180.75. (DISTRICTS #1, #2, #4, #5 & #6) | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
090402
| 0 | | Restoration - Current List | Information Item | Restoration - Current List | | |
Action details
|
Not available
|
100375
| 0 | | Lift Station Pumpage Report | Information Item | Lift Station Pumpage Report | | |
Action details
|