110234
| 0 | | 2012 Concrete Rehabilitation & Utility Cuts Patching | Resolution | FY2012 Concrete Rehabilitation and Cuts Patching, Change Order No. 1
Reflecting an increase of $150,391.20 to the contract with G & M Cement Contractors. (DISTRICTS - ALL) | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
110235
| 0 | | Highland Avenue (22nd-Butterfield) Final Balancing Change Order No. 1 | Resolution | Highland Avenue (22nd-Butterfield) Final Balancing Change Order No. 1
Reflecting an increase to the contract with Illinois Department of Transportation (IDOT) in the amount of $130,328.49. (DISTRICT #3) | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
110257
| 0 | | 2012 Driveway Apron & Sidewalk Restoration Program Change Order No. 1 | Resolution | 2012 Driveway Apron & Sidewalk Restoration Program Change Order No. 1
Reflecting an increase to the contract with Strada Construction in the amount of $70,501.00. (DISTRICTS - ALL) | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
110261
| 0 | | FY2011 Sewer Lining Change Order | Resolution | FY2011 Sewer Lining Program, Change Order No. 1
Reflecting an increase to the contract with Insituform Technologies USA in the amount of $21,672.50. (DISTRICTS - ALL) | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|