230174
| 1 | | Solid Waste Contract for 2024-2029 | Resolution | Solid Waste Contract for 2024-2029
Recommendation from the Public Works and Environmental Concerns Committee and staff that the Board of Trustees approve the 2024-2029 Solid Waste Contract with Waste Management. (DISTRICTS - ALL) | | |
Not available
|
Not available
|
230323
| 1 | | FY2023 Concrete Rehabilitation Program, Change Order #1 | Resolution | FY2023 Concrete Rehabilitation Program, Change Order #1
Reflecting an increase to the contract with G & M Cement Construction, Inc. in the amount of $27,750.00. This increase is needed to adjust the contract quantities to reflect the addition of 1,200 #6 dowel bars used throughout the Village and added traffic control to facilitate the road closures required on Highland Ave. (DISTRICTS - ALL) | | |
Not available
|
Not available
|
230326
| 1 | | FY2023 Snow and Debris Hauling Change Order #1 | Resolution | FY2023 Snow and Debris Hauling Change Order #1
Reflecting an increase to the contract with Nagel Trucking & Materials, Inc. in the amount of $17,265.50. The increase is needed due to the increase in hauling spoils for FY2023 from an increase in emergency excavation repairs as well as planned water and sewer system repairs and maintenance. (DISTRICTS - ALL) | | |
Not available
|
Not available
|
230327
| 1 | | Highlands of Lombard Lift Station Improvements - Omega Electric, Change Order No. 3 | Resolution | Highlands of Lombard Lift Station Improvements - Omega Electric, Change Order No. 3
Approving an extension of contract with Omega Electric. The Contractor has requested an extension by 220 calendar days for a new completion date of May 31, 2024. This is due to supply chain delays. (DISTRICTS - ALL) | | |
Not available
|
Not available
|
230328
| 1 | | 22nd Street Junction Chamber, Change Order #1 | Resolution | 22nd Street Junction Chamber, Change Order #1
Reflecting an increase to the contract with John Neri Construction Company in the amount of $11,500.00. The revised contract amount represents the cost increase associated with installing a pressure connection on the 22nd Street sanitary sewer force main. (DISTRICT #3) | | |
Not available
|
Not available
|