240127
| 1 | | South Park Avenue Pedestrianization Project Change Order No. 2 | Resolution | South Park Avenue Pedestrianization Project Change Order No. 2
Reflecting an increase of $56,192.70 to the contract with R.W. Dunteman Company. This increase reflects additional work improving the sanitary sewer system and the increase of material associated with the concrete roadway, temporary traffic signal and temporary lighting. (DISTRICT #1) | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
240145
| 1 | | Sanitary Sewer Lining Program Change Order No. 1 | Resolution | Sanitary Sewer Lining Program Change Order No. 1
Reflecting an increase of $17,872.00 to the contract with Performance Pipeline, Inc. The revised contract amount reflects additional work for the Cured-In-Place lining of a sanitary sewer located on South Lewis Avenue just south of South Broadway Avenue. (DISTRICT #5) | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
240146
| 1 | | Sanitary and Sewer Sewer Closed Circuit Television (CCTV) Inspection and Cleaning Program Change Order No. 1 | Resolution | Sanitary and Storm Sewer Closed Circuit Television (CCTV) Inspection and Cleaning Program Change Order No. 1
Reflecting an increase of $31,370.46 to the contract with Sewertech LLC. The revised contract amount reflects additional traffic control, cleaning and televising of the storm sewer on North Grace Street and additional sanitary sewer on South Lewis Avenue between South Broadway Avenue and East Washington Boulevard. (DISTRICTS #4 & #5) | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
240165
| 1 | | Responsible Bidder Ordinance | Ordinance | Responsible Bidder Ordinance
Memo presented to the Committee to detail the process of reviewing and evaluating whether the Village of Lombard should adopt a responsible bidder ordinance (RMO). | discussed | Pass |
Action details
|
Not available
|