Meeting Name: Public Works Committee Agenda status: Final
Meeting date/time: 5/9/2006 7:00 PM Minutes status: Final  
Meeting location: Village Hall Community Room
Published agenda: Agenda Agenda Published minutes: Not available  
Meeting video:  
Attachments:
File #Ver.Agenda #NameTypeTitleActionResultAction DetailsVideo
060236 0 FY 06 Underground Structures Change Order No. 1Resolution S. FY 2006 Underground Structure Program - Change Order No. 1 (Resolution) Resolution authorizing Change Order No. 1 to the contract with A Lamp Concrete Contractors to allow a budget transfer in the amount of $14,000 from the Utility Water and Sewer Capital Reserve Fund to the FY 06 Underground Structure Contract increasing the total contract amount to $64,000.00. recommended to the Board of Trustees for approval.Pass Roll call Not available