240217
| 1 | | North Avenue Pressure Adjusting Station Final Change Order No. 2 | Resolution | North Avenue Pressure Adjusting Station Final Change Order #2
Reflecting an increase to the contract with Burke LLC in the amount of $27,966.00. This Change Order includes supplying and installing a meter and a valve motor and deletes a dehumidifier which was part of the original contract. (DISTRICT #4) | | |
Not available
|
Not available
|
240220
| 1 | | FY2025-2034 Capital Improvement Plan Overview | Request | FY2025-2034 Capital Improvement Plan Overview | | |