Monday, December 18, 2006
7:30 PM
Village of Lombard
Village Hall
255 East Wilson Ave.
LombardIL  60148
villageoflombard.org
Village Hall
Plan Commission
Donald FRyanChairperson
Commissioners:  Martin Burke,
Stephen FlintRonald Olbrysh
Ruth SweetserRichard Nelson
and Sondra ZornStaff LiaisonWilliam Heniff
Meeting Minutes
Plan Commission
Meeting Minutes
December 18, 2006
Call to Order
Chairperson Ryan called the meeting to order at 7:30 p.m.
Roll Call of Members
Chairperson Donald FRyanCommissioner Stephen FlintCommissioner 
Ronald OlbryshCommissioner Ruth SweetserCommissioner Martin Burke 
and Commissioner Richard Nelson
Present:
Commissioner Sondra Zorn
Absent:
Also present:  William HeniffAICPSenior PlannerNick HatfieldPrivate Development 
Engineerand George Wagnerlegal counsel to the Plan Commission.
Chairperson Ryan called the order of the agenda.
 
MrHeniff read the Rules of Procedure as written in the Plan Commission By-Laws.
Public Hearings
060588
PC 06-32:  70 Yorktown Shopping Center (the Lombard Westin Hotel/Conference 
Center)
Requesting the Village of Lombard take the following action within the Yorktown 
Peripheral BPlanned Development:
 
Pursuant to Section 155.504(A) (major changes in a planned developmentand Section 
155.511 (Site Plan Approvals for planned developmentsof the Lombard Zoning 
Ordinanceamend the conditional use for the Yorktown Peripheral Planned 
Developmentas established by Ordinance 3962 and amended by Ordinances 4310 and 
5397to allow a further deviation from Section 155.414(E)(4and a variation from 
Section 155.508 (C)(6)(aof the Lombard Zoning Ordinance reducing the required rear 
yard for Lot of the planned development from five feet to 2.feet for an existing 
building encroachment.
(DISTRICT #3)
Chairperson Ryan stated that the petitioner was requesting a continuance of the petition 
until the February 192007 meeting.
It was moved by Commissioner Sweetserseconded by Commissioner Flintthat 
this matter be continued to the February 192007 meetingThe motion carried by 
the following vote:
Aye:
Flint, Olbrysh, Sweetser, Burke and Nelson
5 - 
Absent:
Zorn
1 - 
060652
PC 06-27:  101-125 SMain Street
Requests that the Village take the following actions on the subject propertylocated 
within the BCentral Business District:
 
1.  Approve a conditional use for a planned development with the following variations 
and deviations from the Zoning Ordinance:
 
     a.  A deviation from Section 155.416 (Gto allow for an increase in the maximum 
building height from 45 feet to 48 feet
 
     b.  A variation from Section 155.416 (K)Section 155.508 (C) (6) (band Section 
155.707 (A) (3to allow for a reduction of the required transitional landscape yard from 
10 feet to feet
 
     c.  A variation from Section 155.416 (Mand Section 155.602 to allow for a reduction 
of the required number of off-street parking spaces for a theater from thirty-seven (37
to zero (0);
 
     d.  A variation from Section 155.508 (C) (6) (ato allow for a reduction of the required 
front yard for a planned development abutting the RSingle-Family Residence District 
from thirty (30feet to four (4feet
 
     e.  A variation from Section 155.508 (C) (6) (band Section 155.707 (B) (3to allow 
for the elimination of the required transitional landscape yard improvements
 
     f.  A variation from Section 155.709 (Bto eliminate the requirement to provide one 
(1shade tree for every seventy-five (75lineal feet of required perimeter lot 
landscapingand
 
2.  Approve a conditional use for outdoor diningand 
 
3.  The petitioner also requests Site Plan Approval authority to the Lombard Plan 
Commission.
(DISTRICT #4)
Chairperson Ryan stated that the petitioner was requesting a continuance of the petition 
to the next meeting.
It was moved by Commissioner Olbryshseconded by Commissioner Flintthat 
this matter be continued to the January 222007 meetingThe motion carried by 
the following vote:
Aye:
Flint, Olbrysh, Sweetser, Burke and Nelson
5 - 
Absent:
Zorn
1 - 
060719
PC 06-36:  Roosevelt Road Corridor
Establishment of a nine-month moratorium on new development and/or major 
redevelopment activity along the Roosevelt Road Corridor.  (DISTRICTS #and #6)
William HeniffSenior Plannerpresented the petition.  He introduced the petition and 
submitted the Inter-departmental Review Report to the file in its entirety.
 
He then discussed the proposed moratorium.  The intent of the moratorium is to review 
all land development regulations currently in place affecting development activity along 
the Roosevelt Road Corridor within the Village.  Through this processdevelopment 
regulations would be amended to reflect the goals of the Village's Comprehensive Plan 
and other plans and policies of the Village.  During the moratorium periodstaff would 
review the following issues:
 
A.     Whether a new zoning district classification should be created for the Roosevelt 
Road Corridor or whether an overlay district should be established;
 
B.     The permitted and conditional uses that are/should be allowed within the Roosevelt 
Road Corridorand
 
C.     The bulk regulationssignage and landscaping criteria that are/should be applicable 
within the Roosevelt Road Corridor.
 
He noted that the proposed moratorium would apply to all properties located within the 
Roosevelt Road Corridor that are either zoned for or utilized as commercial uses.  The 
moratorium would temporarily put a hold on the following activities within the Corridor:
 
1.     Any construction of a new principal building;
 
2.     Any construction of an additionto an existing principal or accessory buildingof 
more than 500 square feet in size;
 
3.     Any new freestanding signshowevertemporary signs and panel face changes 
would be exempt from the moratoriumand
 
4.     Any change in the type of commercial use for an existing commercial space of 5,000 
or more square feet of gross floor area.
 
Projects approved by the Village prior to the establishment of the moratorium would be 
exempt from the moratorium provisionsprovided that construction begins on the project 
within one (1year of the date of approval.
 
He then discussed the genesis of the moratorium concept.  He noted that in the past 
staff has worked on a number of development issues along the Butterfield Road corridor 
to enhance its viability.  Notable examples included the Fountain Square and Highlands 
of Lombard planned developments as well as the Yorktown Mall/Shops on Butterfield 
improvements.  With these approvals in placethe Village Board in its strategic planning 
sessions has asked staff to turn its attention to the Roosevelt Road corridor.  
Specificallythe Board directed staff to begin a comprehensive review of the corridor to 
determine what actions should be undertaken to address development concerns and 
economic impacts of redevelopment within the corridor.
 
He noted that Roosevelt Road is a primary commercial corridor and a Strategic Regional 
Arterial roadway within the Village.  It is essential that the zoning and development 
regulations established for properties within the corridor reflect the goals set forth within 
the Comprehensive Plan and reflect the desires of the community.  Also of great 
importance is the goal to ensure that the economic vitality of the corridor is maintained 
and enhanced.
 
He noted that a number of properties within the corridor are currently in transitionThese 
properties currently have or may have significant vacancies in the near future.  Other 
sites are slated for development or redevelopment activity.  At the same timeproperty 
owners and developers are asking staff to provide comment on prospective 
development plans or provide direction regarding their proposals.  While staff could 
direct inquirers back to the relevant Village Codesstaff believes it is more important to 
undertake a greater overall analysis of the corridor to determine if the Village Codes 
would actually produce the desired output
 
He then referenced several submitted exhibits depicting the existing conditions along the 
corridor.  These included the existing land usethe Comprehensive Planthe existing 
zoning districts and an aerial of the corridor.  He noted that the corridor is currently 
designated for community commercial uses within the Comprehensive Plan.  The 
existing zoning along the corridor is a patchwork of Band Bpropertiesmany of which 
are also controlled by planned development approvals.
 
He then stated that the intent of the moratorium is to review all land development 
regulations currently in place that would affect development activity within the corridor.  
Through this processdevelopment and zoning regulations would be amended that 
reflect the goals of the Comprehensive Plan and other adopted plans and policies of the 
Village.  The intent of the analysis is also intended to look at the corridor 
comprehensively rather than reviewing the properties on an individual basis.
 
He noted past reviews undertaken by the Village including the establishment of the B5
zoning district.  He noted that the corridor review can be considered a first step as part 
of an update to the Village's Comprehensive Plan.  He also referenced past efforts along 
the East StCharles Road corridor in the late 1990s.
 
He noted that many of the Roosevelt Road properties abut residential properties and 
what the appropriate treatment for the transitional yards would be.  Future analysis will 
include design aspectssignagelandscapingand curb cuts
 
He identified the issues and items that may be reviewed during the moratorium period
as referenced within the staff report.  The final analysis may not necessarily include 
recommendations to amend all of the areas to be reviewed.  There are a number of 
tools that will be reviewed including establishing a new zoning districtcreating a corridor 
overlay districtdevelopment design guidelinesand/or establishing more form-based 
zoning regulations
 
Questions were previously raised to staff about the need for a moratorium.  He stated 
that staff would not want to see the Village being placed in the position of reviewing 
projects slated to start in 2007 with one set of regulations and others that will start in 
2008 with another set of regulations.   As such the proposed moratorium would serve as 
a temporary “time-out” while all aspects of the corridor are reviewed.
 
The moratorium is intended to extend for a nine-month period.  Within this timeframe
the first six-month period would consist of a comprehensive review of the study 
elements andif necessaryan additional three-month period is also suggested in order 
to allow any affected codes that would be amendedto be properly considered through a 
separate public hearing and/or committee review processes.   
 
In addition he noted that in anticipation of the moratoriumstaff also sent out notices to 
all property owners and known business tenants.  Staff also held an informational 
meeting on December 62006 to review the moratorium concept with the affected 
property owners and/or business tenants.  General concerns about the moratorium and 
its applicability to specific properties were discussed.  Staff noted that if a project is 
deemed necessary and desirable by the Village Boardan exemption from the 
moratorium could be approved for a specific project.
 
He referenced the appendices within the staff report that depicted the moratorium area
the topics to be reviewed and a draft Ordinance for discussion and review.
 
He closed his presentation by noting some of the comments previously raised to staff 
including exemption provisions and change of use provisions
 
Chairperson Ryan then opened the meeting for public comment.
 
John Moroniowner of the Westgate Lincoln Mercury property500 ERoosevelt Road
inquired further about the exemption provision.  He also asked if the moratorium would 
allow for a new automotive establishment to be located on his property.  MrHeniff noted 
that the intent of the ordinance is to provide an opportunity to allow for a like use to 
occupy the premisesbut not a change of use.
 
MrMoroni stated that it may not be a smart move to have a property vacant for a 
nine-month period and asked if there is a possibility for an exemption.  MrHeniff stated 
that the staff report and recommendation notes that if the Board finds that a project is of 
a substantial design and is consistent with the objectives of the corridor reviewthe 
Board could grant special exception.
 
Mark Blum400 Skokie BoulevardNorthbrookrepresents Roosevelt Associatesowner 
of a shopping center within the corridor.  He noted his existing tenants include Sports 
AuthorityFruitful YieldMarshall's and X-Sport Fitness.  He noted that the original 
Sportmart was located within the center.  He raised concerns regarding the change in 
use provisionsnoting that they do not want to be negatively impacted by the proposed 
moratorium as it pertains to their ability to re-lease vacant tenant spaces.  MrHeniff 
noted that the intent of the ordinance is to provide for similar retail uses to be able to 
occupy tenant spaces.  He noted the example that if a sporting goods store would leave 
the center that a similar retail usesuch as a clothing storewould be permissible.  
Howeverif it were to change to a differing land use such as an office useit would not 
be a permitted exception to the moratorium.
 
Peter Friedmanattorney for Roosevelt Associatessought a clarification regarding the 
change of use provisions.  He noted that the draft ordinance is vague relative to this 
issue.  He also stated that the draft ordinance does not specifically state the exemption 
provisions.
 
George WagnerVillage Counselnoted that projects previously approvedwould fall 
under the exemption provision.  
 
John Hirsh III53 NMain StreetGlen Ellyndiscussed his concerns regarding the 
exceptions to the moratorium ordinance.  He asked about the process that would be 
involved to get a hearing for an exemption from the moratoriumspecifically as it relates 
to the Westgate property.  MrHeniff stated that the site is already regulated by a 
planned development.  Any changes to a planned development would be required to go 
to the Plan Commission and Village Board for consideration.  This is typically a 90-day 
process.  Howeverhe noted that before considering an exception to the moratorium
staff would want to know what was being proposed for a site.
 
MrHirsh noted that a prospective developer inquired about his property and met with 
staffbut staff did not want to review his concept plans for the site.  MrHeniff noted that 
staff discussed the proposed moratorium with the prospective developer.  Howeverin 
light of the proposed moratoriumit would be presumptuous for staff to provide 
comments and recommendations on the plansas such recommendations may or may 
not reflect the ultimate goals of the corridor study.  That is why staff wanted to start this 
review process.
 
MrHirsh asked if it is possible to get exemption from the Board.  MrHeniff stated that 
the first step in this process is to get Board approval of the moratorium concept.  The 
second step would be to create an ad-hoc groupfollowed by the commencement of a 
review of the relevant issues and establishing recommendations.  Staff does want the 
process to be participatory with the property owners and tenants along Roosevelt Road.
 
MrHirsh noted that there is limited interest in the domestic car market for retail stores 
and the import dealer radii limits ability of his site to be used for an import dealership.  
The nine-month period would create a hardship.
 
Chairperson Ryan then opened the meeting for comment among the Plan Commission 
members.
 
Commissioner Sweetser noted there is merit in looking at the corridor comprehensively.  
She inquired about other efforts that may have been done in the past and asked if the 
quick timeframe will be workable.  MrHeniff noted that the nine-month review period is 
an aggressive timeline to be fair to property owners.  He also noted that this process 
could be a model for future corridor reviews.
 
She then asked if the exemption provisions were spelled out properly within the draft 
ordinance.  MrHeniff said that staff will review that issue with Counsel.
 
MrWagner noted that the Plan Commission could provide specific concerns within the 
recommendation of approval.
 
Commissioner Burke inquired about clarifying what previously approved projects would 
be subject to the exemption provision.  MrHeniff noted that projects that were 
previously approved by the Board prior to the establishment of the moratorium would be 
exempt.  As an examplehe noted an approved project at the corner of Highland 
Avenue and Roosevelt Road.  Since the Board approved the zoning actionsthe 
petitioner could start construction on the projectprovided that the construction activity 
starts within one year from the date of the final approvalwhich is April2008.  Other 
properties which did not require Board approval could start provided that a permit was 
issued prior to the start of the moratorium.
 
Commissioner Burke stated that it is not clear as to what projects would or would not be 
subject to the exception provision in the moratorium and he asked that the Ordinance 
clarify this issue.  
 
Commissioner Burke then referenced an unincorporated property west of the existing 
Village limits.  And asked how those properties should be handled.  MrHeniff noted that 
the annexation agreement would provide even greater authority than a moratorium.
 
Commissioner Burke then asked about the boundary agreement between Lombard and 
Glen Ellyn --would the moratorium affect the agreement?  MrHeniff said the moratorium 
would not affect the boundary agreement.
 
Commissioner Sweetser asked what affect the moratorium might have on annexing 
properties in general.  MrHeniff noted that an annexation agreement would provide 
greater control then even the proposed moratorium.  The future ad-hoc group charged 
to review the development issues would not review unincorporated properties as they 
are not part of the moratorium
 
Commissioner Nelson inquired about a proposed overlay district.  MrHeniffnoted that 
overlay districts create additional regulations about those provided for within an 
underling zoning district.  He noted that the Village previously established such a district 
along the North Avenue corridor in the early 1990s
 
Commissioner Olbrysh stated he would not want to see a lot of exceptions to the 
proposed moratorium.  He referenced the statement regarding the exceptions within the 
standards for text amendments and wanted clarity on this issue
 
Chairperson Ryan sought a clarification regarding who received notice of the proposed 
moratorium.  MrHeniff noted that the Village sent notices of the public hearing to all 
property owners.  We sent notices of the informational meeting held on December 6
2006 to all property owners and all known businesses within the corridor.
 
Commissioner Flint asked if the moratorium could extend beyond the proposed 
nine-month periodMrHeniff stated that it is not staff's intent to go beyond a nine-month 
period.  He noted that if it was to extend beyond the nine-month perioda new petition 
would need to be filed.  MrWagner noted support within the court for a 6-month 
period.
 
Commissioner Sweeter stated that the exemption provision for past approvals needs to 
be clarified.  Commissioner Burke requested consistency within the ordinance for clarity 
to protect people with permits already approved.
 
MrWagner stated that the Plan Commission can note within their recommendation the 
three elements that the Commissioners would like to see reviewed within the report
including clarity on past approvalsexemption provisions and change of use provisions.
It was moved by Commissioner Sweetserseconded by Commissioner Burkethat 
this matter be recommended to the Board of Trustees for approval subject to the 
following amendments to be made to the final draft OrdinanceThe motion 
carried by the following vote:
Aye:
Flint, Olbrysh, Sweetser, Burke and Nelson
5 - 
Absent:
Zorn
1 - 
1.  That the change of use provisions be more thoroughly addressed;
2.  That the Ordinance be clarified as it pertains to the properties or projects that would 
be except from the Ordinanceand
3.  That the Ordinance addresses the provisions for establishing exceptions to the 
moratorium.
Business Meeting
Chairperson Ryan convened the business meeting at 8:20 p.m.
Approval of Minutes
1.  The minutes of the November 202006 Plan Commission meeting were unanimously 
approved by the members present with the following amendment:
 
     Commissioner Sweetser stated that the minutes were grammatically wrong as there 
were shifts in first and third person tense.  She suggested that the tense be changed to 
keep consistency.      
 
2.  The minutes of the November 272006 Special Plan Commission meeting were 
approved by unanimous consent of the members present with the following correction:
 
     George Wagnerlegal counsel to the Plan Commissionamended the top of Page 5
to read as follows:
 
     "Telecommunication Act of 1996 specifically preempts the Village from considering 
environmental effects of radio frequency emissionsso long that...."
Public Participation
There was no public participation.
DuPage County Hearings
There were no DuPage County hearings.
Chairperson's Report
Chairperson Ryan deferred to the Senior Planner.
Planner's Report
William Heniff noted that the next Plan Commission meeting was rescheduled from 
January 152007 to January 222007 in lieu of the Martin Luther King holiday.
 
MrHeniff also introduced Nick Hatfieldthe new Private Development Engineer for the 
Department of Community Development.  Dave Gormanthe individual who previously 
held this positionhas been promoted to the Assistant Director of Public Works.  Mr
Hatfield will take on the responsibilities previously completed by MrGorman.
Unfinished Business
There was no unfinished business.
New Business
There was no new business.
Subdivision Reports
There were no subdivision reports.
Site Plan Approvals
There were no site plan approvals.
Workshops
There were no workshops.
Adjournment
The meeting adjourned at 8:30 p.m.
 
 
____________________________________
Donald FRyanChairperson
Lombard Plan Commission
 
 
____________________________________
William HeniffAICPSenior Planner
Lombard Plan Commission