1.0
Call to Order and Roll Call
The meeting was called to order by Chairperson Gatz at 7:30 p.m.
Trustee Frank MGatz Sr., Committee Member Trustee Joan DeStephano, 
Gordon Hallbeck, David Arnold, Stephen Preins and John Kaforski
Present:
Trustee Ralph Borgatell and John Meyer
Absent:
2.0
Public Participation
Geri Mejia  507 WEugenia
Mary Law   427 WEugenia
Steve Sweetser   431 WEugenia
Mark Ahlenius   22 NGlenview
Steve Freetly   518 WEugenia
Bill Coons   162 ESunset
Jim Royhl   506 WEugenia
Juan Marceco, Jr.   527 WEugenia
Monica Kelley   527 WEugenia
Frank Lahey   40 NGlenview
3.0
Approval of Minutes
4.0
Old Business
980210
Robert Lewis reviewed the preliminary report.  Laterals and manholes are the biggest 
causes of inflow and infiltration in the area.  The sanitary sewers on ESunset, N
Garfield, WGoebel and WPotomac need complete repairs to improve capacity 
problems.  Robert asked for a concensus from the committee to begin strategic repairs 
as outlined:  Replace manholes and perform structural repairs on the above listed 
sewers.  The area west of Main Stwould be completed first with the road construction 
project.  The remainder would be budgeted for upcoming years.  There was a 
concensus among the committee members to proceed per staff recommendation.
 
The committee also recommended that staff continue to look for ways to reduce the 
inflow and infiltration in this area and add this to the CIP as a separate project to be 
budgeted for.
 
MrCoons asked if any of this would help his flooding problem.  Robert and the 
committee explained to him that any incremental work will help him.  Robert also 
explained that for Sunset he would recommend replacing the sanitary line and installing 
a larger sewer to take the additional flow from inflow and infiltration.  Right now there is a 
50chance of a surcharge on that line.  With the recommended repairs it should drop 
to a 10-20chance of a surcharge in a rain event.
5.0
New Business
980211
Stan Rickard reviewed the recent events with the committee.  Eugenia is part of Special 
Assessment 213/214 scheduled for 2000/2001.  The policy for basic public 
improvements is 28' street, curb and gutter, storm sewer, sidewalks on both sides, trees 
and street lights.  The residents of Eugenia are asking that no sidewalk be installed and 
the street not be widened.
 
Stephen Preins pointed out that with that policy we're talking about a typical street.  
Eugenia is not a typical street.  It is certainly an exception.
 
Robert Lewis explained that it is a policy issue and will have to go to the Board of Local 
Improvements.  Staff could bring a recommendation to BOLI not to install sidewalk and 
street lights.
 
Mark Ahlenius wanted to make sure that the turning radius would not be a problem for 
the Fire Department.  Robert Lewis responded that there would probably be a parking 
ban on Eugenia.  Mark felt that people would be OK with that as long as they did not 
lose their mature trees.
 
Mark informed the committee that Trustee Ralph Borgatell is "forthe residents view on 
this.  Mark also stated that he hopes the Board of Trustees would heed a 
recommendation from the Public Works Committee.  Mark also if they only redo the 
street, would the residents be charged for a full improvement?  Stan Rickard referred 
that question to the committee.  If there were a lesser improvement would the committee 
agree to a lesser assessment?  There was a concurrence among the committee 
members to charge a lesser assessment.
 
Monica Kelly was concerned that if the road goes any higher it would increase her 
flooding problems.  Stan Rickard explained that many times they lower the road.  Robert 
Lewis confirmed also that drainage is looked at with every project.
 
Steve Freetly asked if the road were reconstructed would the village still put in a storm 
sewer.  Robert Lewis responded that it would be a protection of our investment.  He also 
suggested that the residents work with Public Works Committee and BOLI for some type 
of improvement rather than do nothing at all.  That way, maybe you will get something 
that everyone can live with.
It was moved by  Hallbeck, seconded by  Preins, that the Public Works Committee 
recommend to the Board of Local Improvements that improvements on Eugenia 
include only new street and modified curb not to be widened beyond the existing 
width.  The motion carried by the following vote:
Aye:
Hallbeck, Arnold, Preins and Kaforski
4 - 
6.0
Change Orders
980192
R E S O L U T I O N
R_______________98
 
A RESOLUTION AUTHORIZING A CHANGE ORDER
INVOLVING AN INCREASE IN THE DOLLAR AMOUNT OF  THE CONTRACT OF $10,000 OR 
MORE
It was moved by  Hallbeck, seconded by  Preins, that this matter be recommended 
to the Board of Trustees for approval.  The motion carried by the following vote:
Aye:
Hallbeck, Arnold, Preins and Kaforski
4 - 
Enactment NoResolution 92-98
7.0
Pending Change Orders
Robert Lewis reviewed the pending change orders.
8.0
Other Business
John Kaforski asked if staff could find a better way to mark trees for trimming.  People 
are complaining about the white dots, because they do not fade quickly.
Stan Rickard assured him staff would look into an alternate method.
 
John Kaforski spoke to staff regarding his concern for the morale of the employees.  
With such a large CIP he wanted to be sure morale was not jeopordized.
 
Gordon Hallbeck asked what is going on with all the water in the street on SFairfield.  
Stan Rickard explained that it is overland flow and Public Works will be installing some 
edge drains
 
David Arnold suggested that when the permanent work is done to the intersection of 
Highland and Washington, that maybe it could be done after school lets out to avoid 
having the heavy equipment around the kids.  Stan Rickard asked if would be 
acceptable to do it soon if it were performed in two consecutive days.  David Arnold was 
agreeable to that but wants the school notified prior to the work.
 
Joan Destephano asked if StCharles Road could be plowed differently.  The windrow 
makes it impossible to make a left turn off of Lincoln.  Stan Rickard explained that it is 
village policy to remove the windrow that night.  The reason for the windrow is to avoid 
snow being stacked on the downtown sidewalks.
9.0
Information Only
970045
Concoord 
970046
Restoration List 
970047
Procurement Schedule 
970153
Construction Barricade Reports (light deficiencies
980212
Change Order Report 
10.0
Adjournment
It was moved by  Hallbeck, seconded by  Kaforski, that there being no further 
business the meeting is adjournedThe motion carried by a voice vote