Tuesday, October 9, 2007
7:00 PM
Village of Lombard
Village Hall
255 East Wilson Ave.
LombardIL  60148
villageoflombard.org
Village Hall Community Room
Public Works Committee
Trustee Richard JTross-Chairperson
Trustee Jack O'BrienAlternate Chairperson
John KaforskiArthur KuehlDavid Arnold,  Art Frerichs,
Ken Blakeslee and Dan Mahal
Staff LiaisonsWes Anderson and David Dratnol
Meeting Minutes
REVISED
Public Works Committee
Meeting Minutes
October 9, 2007
1.0
Call to Order and Roll Call
Meeting was called to order by Chairperson Tross at 7:04 PM.
Richard J.  TrossDavid ArnoldKen BlakesleeDan MahalArthur Kuehl and 
Art Frerichs
Present:
John Kaforski
Absent:
2.0
Public Participation
Heather Murphy, 1580 S. Lloyd Ave., Lombard
3.0
Approval of Minutes
It was moved by  Frerichsseconded by  Mahal,  to approve.  The motion carried 
by a voice vote
4.0
Unfinished Business
070400
Backyard Drainage Grant Program Commercial.
Will table this until all committee members are present at a meeting.
It was moved by  Mahalseconded by  Kuehlthat this matter be tabled.  The 
motion carried by a voice vote
070588
Mailbox Policy
Approving a policy concerning replacement of mailboxes impacted by snow removal 
operations.
Tross:  survey was to be taken so that we can see what is out there.  Frerichs:  I don'
see a problem with this type of mailbox on a residential street where speed limit is lower.  
Murphy:  I do not see the difference between a treea poleetcand my mailbox.  
Discussion ensued.  Tross:  why are we sending out letters to these people?  Are we 
singling them out?  Anderson:  nothese letters are only sent out when we get a 
complaintetcregarding a structure in the right-of-way.  Tross:  the Murphy's were not 
part of the survey that we are doingAnderson:  we were informed about the structure 
in the right-of-way from Community Development or another source.  It was brought to 
our attention and we had to investigate it.  Kuehl:  a structure like this would need to 
have a permit.  It is a permanent structure.  If you would have applied for a permitit 
would have been stopped right away.  Tross:  let's take the policy first.  Explain to the 
committee how you intend to tell people about violations.  Anderson:  if it is just a 
distance issue  we will have a form letter or door hanger that we will distribute.  Tross:  
are you surveying the entire rural route of Lombard?  Anderson:  we will have to.  Kuehl:  
we are trying to protect the Village here.  Tross:  was that the intent of the committee?  
Consensus of the committee was yesthat was the intent and want to bring this policy 
back to the board.  
Tross:  what can we do about the MrsMurphy issue?  Anderson:  it will have to be 
brought to the board requesting a variance.  Staff cannot do thisit needs to be 
approved by the board.  Tross:  asked Anderson how to obtain variance/how to appeal.  
Dratnol:  staff can address the issue with Tom Bayer.  Mahal:  letter does say "30 days"
is that enough time to handle this?  Anderson:  normally if code enforcement sends the 
letterthe resident is given only 10 days.  We would need to create a memo to address 
the issue.  There are certain instances that staff does have the power to issue a 
variance.  We will have to look into this ordinance specifically to see what we can doif 
anything.  Tross:  directed staff to bring this issue back to the next meeting with 
information about variances.
It was moved by  Blakesleeseconded by  Kuehlthat this matter be recommend 
to the Board of Trustees for Approval.  The motion carried by a voice vote
5.0
New Business
6.0
Ratification of Agreements
070581
FY 2008 Concrete Rehabilitation And Utility Cuts Patching
Change Order No1Authorizing an increase to the contract with Kings
Point General Cement in the amount of $91,048.00.
It was moved by  Mahalseconded by  Blakesleethat this matter be 
recommended to the Board of Trustees for approval.  The motion carried by the 
following vote:
Aye:
Arnold, Blakeslee, Mahal, Kuehl and Frerichs
5 - 
Absent:
Kaforski
1 - 
Enactment NoResolution 34-08
7.0
Other Business
070597
Village-Wide Transportation Study Draft Purpose And Scope Of Work
Anderson:  reviewed this item with Committee members.  Tross:  has this already been 
approved in the budget?  Anderson:  yes.  Kuehl:  don't we have something similar to 
this?  Anderson:  similar but this is much more conceptual.
8.0
Information Only
970045
Project Status Report
980212
Change Order Report
030008
Engineering Monthly Report
9.0
Adjournment
Tross:  informed committee members that they have all been re-appointed for another 
years.  There has been much discussion at the board level about committee members.  
Committee members are not official representatives of the Village.  Any issues need to 
go through the committees.  Tross:  need PWC members to volunteer on the 
Community Forum.  This is the second go around.  Would like members from this 
committee.  Forum is being held on SaturdayOctober 27th.  Frerichs will check his 
availability.  John Kaforski and Dave Arnold were volunteered for the assignment.  
Anderson:  announced that he is taking a position as Public Works Director in 
GreenvilleNC.  Last day will be 11-to 11-9.
It was moved by  Frerichsseconded by  Mahalto adjourn at 8:04 PMThe motion 
carried by a voice vote