Tuesday, February 3, 2004
7:00 PM
Village of Lombard
Village Hall
255 East Wilson Ave.
Lombard, IL  60148
villageoflombard.org
Village Hall Community Room
Public Works Committee
Trustee Steven DSebby, Chairperson
Trustee Rick Soderstrom Vice Chairperson
John Kaforski, Rick Mahal, David Arnold,  Art Frerichs,
Ken Blakeslee and Dan Mahal
Staff LiaisonsWes Anderson and David Dratnol
Meeting Minutes
Public Works Committee
Meeting Minutes
February 3, 2004
1.0
Call to Order and Roll Call
The Special Meeting of the Public Works Committee of February 32004 was called to 
order by Chairperson Steven Sebby at 8:25 p.m.
Chairperson Trustee Steven DSebby, John Kaforski, David Arnold, Ken 
Blakeslee, Dan Mahal and Art Frerichs
Present:
Rick Mahal
Absent:
Appointed Officials in Attendance:
 
Acting Director of Public Works John Burg
Village Engineer David Dratnol
Deputy Village Clerk Barbara Johnson
2.0
Public Participation
None
3.0
Approval of Minutes
Approval of the minutes of the January 13, 2004 meeting.
It was moved by  Blakeslee, seconded by  Kaforski, to approveThe motion 
carried by a voice vote
4.0
Unfinished Business
Chairperson Sebby noted that some pending items such as traffic calming, 
improvements to West  Wilson, the street lighting project and as directed this evening, 
sidewalk programs will be addressed at the March meeting.
 
David Arnold commented on the traffic calming CD they received and said that he would 
like to see some device at Finley and Wilson, a very congested area.  He added that as 
long as improvments are going to be done there, traffic calming could be done at the 
same time
 
Dan Mahal suggested that traffic calming be done at Main and the Prairie Path as well 
as at Westmore/Meyers and the Prairie Path.  Some discussion ensued regarding the 
fact those were the only two four lane roads one had to cross while on the Path.  
Trustee Sebby mentioned that perhaps there are test programs out there that would 
eliminate the Village having to fund the traffic calming.
 
John Burg suggested that since the Committee of the Whole and Public Works 
Committee meeting was held previously, the subject of traffic calming be discussed at 
the next meeting.
5.0
New Business
030876
H.  FY 2004 Dust Control Program Final Change Order #(Resolution)
Resolution authorizing Final Balancing Change Order Noto the contract with Boecker 
Road Maintenance reflecting a $32,250 decrease due to the termination of the contract.  
(DISTRICT ALL
David Dratnol explained that this is really a matter of  paper work to close out a 
terminated contract.
It was moved by  Arnold, seconded by  Mahal, that this matter be approvedThe 
motion carried by a voice vote
Enactment NoResolution 88-04
030906
J.  Prairie Path Lighting Change Order No(Resolution)
Resolution approving Change Order Noto the contract with Aldridge Electric, Incin 
the amount of $19,749.50 for work associated with the Prairie Path Lighting project
(DISTRICTS #& #5
MrDratnol explained the increase in amounts, saying that it represents as-measured 
quantities of directional boring, conduit pushed in place, and a deduct for unit duct 
length.  It also adds four poles, and additional house side shields which would have 
been added if residents wanted, but they decided that they would include them in the 
contract.
It was moved by  Arnold, seconded by  Blakeslee, that this matter be approved
The motion carried by a voice vote
Enactment NoResolution 90-04
030919
N.   Lombard Hills East (Phase IV) (Resolution)
Resolution approving Final Balancing Change Order Noto the contract with RW
Dunteman Company reflecting a decrease of $51,321.27 for the total quantities 
associated with the Lombard Hills East (Phase IVproject.  (DISTRICT #4
MrDratnol said that the increases where due to small added handholes and some 
splicing that needed to be done.  Some of the lighting had to be temporarily  spliced into 
new lightingHe said that conduit had to be pushed under Goebel and that cost had 
been omitted from the original contract.
 
Trustee Sebby questioned whether there was any way to have avoided the handholes 
and Dratnol explained that either the handholes had to be used or the wiring rerouted 
due to the small poles in the area.  He further explained that  these poles are smaller 
than at major intersections.
 
Dan Mahal questioned the protective coating.  MrDratnol explained that it is usually 
included in contracts to prevent salt damage.
It was moved by  Mahal, seconded by  Frerichs, that this matter be approvedThe 
motion carried by a voice vote
Enactment NoResolution 92-04
6.0
Other Business
Art Frerichs complimented Green Horizon and the work that they do with sidewalks
John Burg said that sidewalks were actually done by a different company and he would 
pass these comments on.  There was some discussion of snow removal on business 
and residential sidewalks  Trustee Sebby said that he will talk to Community 
Development Director David Hulseberg and have Code Enforcement observe and write 
violations.
7.0
Information Only
970045
Concoord 
030008
Engineering Monthly Report 
8.0
Adjournment
It was moved by  Frerichs, seconded by  Mahal, to adjourn at 8:50 p.mThe 
motion carried by a voice vote