Tuesday, October 14, 2008
7:00 PM
Village of Lombard
Village Hall
255 East Wilson Ave.
LombardIL  60148
villageoflombard.org
Village Hall Community Room
Public Works Committee
Trustee Richard JTross-Chairperson
Trustee Jack O'BrienAlternate Chairperson
John KaforskiArthur KuehlDavid Arnold,  Art Frerichs,
Ken Blakeslee and Dan Mahal
Staff LiaisonDavid Dratnol
Meeting Minutes
Public Works Committee
Meeting Minutes
October 14, 2008
1.0
Call to Order and Roll Call
Meeting called to order by Chairperson Tross at 7:02 PM.
Richard J.  TrossJohn KaforskiDavid ArnoldKen BlakesleeDan Mahal
Arthur Kuehl and Art Frerichs
Present:
2.0
Public Participation
Lorri Ostruszka 297 NLewis
Madeleine McAfee 720 EPrairie
Paul KuehlenzPublic WorksCivil Engineer
 
Ostruszka:  what is going to happen with the pond?  Called PW about the pond being 
high at least times before the 9/12-13 storm.  There was no plan by PW to handle the 
rain from this storm.  McAfee:  we had overland flooding on all four sides of our homes.  
Ostruszka:  there seemed to be no plan for this event by PW.  Kaforski:  you called well 
in advanceI would be upset also.  Tross:  addressed the policy as far as the sandbags 
are concerned.  Discussion ensued regarding previous construction (CHAW project).  
Tross referred to combined sewer systems and how the flow from the Vista Pond effects 
those residents.  Engineering Staff is looking at the pond to see what options there are.  
McAfee:  the pond is in our backyards 2-times per year.  We all want to know what 
went wrongwhy was there no quick responsewhat is the short term plan and then if 
there is a long term plan.  Kaforski:  there needs to be an interim planand the residents 
need to be informed of what the plan is.  Tross:  bring back the storm plan to the next 
meeting and the committee will give direction/changes.
3.0
Approval of Minutes
It was moved by  Kuehlseconded by  Frerichs,  to approve.  The motion carried 
by a voice vote
4.0
Unfinished Business
070307
Proposed Policy for Street Side Mailbox Replacement Impacted by Snow Removal 
Operations
Gorman:  reviewed memo with the committee.  Kaforski:  check with attorney prior to 
this going any further.  Arnold:  is there a policy as to how close the plow needs to plow 
towards the curb?  Tross:  yesthere is.  Discussion ensued regarding York Township'
mailbox replacements.  Gorman:  there are structural mailboxes.  Need to notify 
non-compliance to codes check with attorney regarding liability of Village.  Gorman:  
this would be handled by the Code Enforcement Division.  
Committee directed staff to draft letter to 317 people.  In the letter and item say 
become compliant or what???  Tross:  check with attorney to see if we have the right to 
remove it and replace it.  The liability issue is what the questions are about.  We give 
them a deadline to remove and replace.  Hand over list of 2,237 mailboxes to post 
office.  Same letter will go to all violators.  Submit this to committee at the next meeting.
Gorman:  second part is that we are looking for reimbursement policy.  Tross:  we could 
do what we do with reconstruction and tell them that when it is ready to be reinstalled
we will reinstall it.  We took it outwe should install it.  Goldsmith:  we could revise this to 
read that if we took it outwe could install it.  Committee would like PW to install 
replacements.  Just replace with a standard mailbox.  Committee directed staff to draft 
revised policy and bring copies of letters to next meeting.
It was moved by  Kaforskiseconded by  Arnoldthat this matter be tabled.  The 
motion carried by a voice vote
080628
Update on Grace Street Whitetopping.
Dratnol:  reviewed findings with the committee.  Discussion ensued regarding grind and 
overlay vswhitetopping.  Dratnol:  would not recommend whitetopping on the average 
residential street in Lombard.  Should be done on the more heavily traveled streets.  
Whitetopping is ground inches.  Tross:  looking for a direction from the committee 
regarding going out for bid on whitetopping.
Tross:  BlacktopConcrete or Whitetopping adopt a policy and let PW Engineering 
administer it.  Put flexibility there.  Change the street policy not make it asphalt to 
asphaltconcrete to concreteetc.  Directed staff to bring policy to the Village board  
regarding bidding process involving this.
5.0
New Business
080567
Special Assessment 217AChange Order No2
Authorizing a decrease in the amount of $137,501.41 to the contract with R.W
Dunteman Company.  (DISTRICT #4)
It was moved by  Frerichsseconded by  Kaforskithat this matter be 
recommended to the Board of Trustees for approval.  The motion carried by the 
following vote:
Aye:
Kaforski, Arnold, Blakeslee, Mahal, Kuehl and Frerichs
6 - 
Absent:
John O'Brien
1 - 
080575
FY 2009 Concrete Rehabilitation and Utility Cuts Patching Change Order No1
Reflecting an increase to the contract with Triggi Construction in the amount of 
$96,955.00.  
Fire Station 1 - added to the existing contract.
It was moved by  Frerichsseconded by  Kaforskithat this matter be 
recommended to the Board of Trustees for approval.  The motion carried by the 
following vote:
Aye:
Kaforski, Arnold, Blakeslee, Mahal, Kuehl and Frerichs
6 - 
Absent:
John O'Brien
1 - 
080602
Main Street Lighting Phase I Change Order No3
Reflecting an increase of $38,712.91  to the contract with Utility Dynamics.  (DISTRICTS 
#1, #2, #4, #5, & #6)
Dratnol reviewed the items on the change order with the committee members.  
Discussion ensued.  Tross:  questioned the design engineering on the project.  Dratnol:  
this is not the fault of the design engineering.  Until you physically dig into the ground
you cannot see what is there.  Further discussion ensued.  Kaforski:  aren't some of 
these charges pursuant to the ComEd fiasco?  Dratnol:  we could try to get more from 
ComEd.  I have no problem with that.  Tross:  I can appreciate the time extensionbut 
the issue of ComEd hitting the sanitary sewer had nothing to do with holding this up.  My 
issue is with the contractornot with ComEd.  The poles are cockeyedwires are 
hanging on our new polesscratching them.  We are still waiting for Comcast to relocate 
their lines.  Goldsmith:  this is an ongoing project.  Dratnol:  if the utility companies have 
not finished their workthe contractor cannot proceed.  We do not have any leverage or 
control over the utility companies.  They need to finish moving their facilitieswe can 
only tell themwe cannot force them.  Tross:  there are lines hanging all over the place.  
ComEd has done their jobit is the other utilities that have not finished their work.  
Dratnol:  I cannot tell them when need to be out there.  I have no control over them.  
This has to do with the project.  There are change conditions on this project that you 
cannot plan for.  Tross:  this whole job is becoming a comedy of errorsand no one 
cares about it.  When are these lines going to be moved?  Dratnol:  I cannot tell you 
when this is going to happen.  Kaforski:  is there anyone there that you can talk to?  
Dratnol:  we talk to them on a daily basis.  Goldsmith:  there is no disservice to the 
residents at this point but there will be if we would disrupt their service.  Dratnol:  the 
contractor is obligated to fixaccording to our specificationsany damage to the finish on 
these poles.  Kaforski:  I understand the items on these change orders.  Dratnol:  there 
is legislation that is in place.  The Village Clerk needs to send a letter to the utility 
companies to let them know what we are going to need done by them.  That is all we 
can do.  Goldsmith:  contractor needs to be paid.  We will continue to monitor the utility 
companies.  We will continue to do what we can to get the issue resolved.  But the 
bottom line is that the contractor needs to get paid.    Further discussion ensued.  
Kaforski:  would like to see in writing the amounts that we are going to try to be 
reimbursed for from ComEd.  Directed Dratnol to bring these to the next meeting.
It was moved by  Kaforskiseconded by  Arnoldthat this matter be recommended 
to the Board of Trustees for approval.  The motion carried by the following vote:
Aye:
Kaforski, Arnold, Blakeslee, Mahal, Kuehl and Frerichs
6 - 
Absent:
John O'Brien
1 - 
080604
FY 2009 Asphalt Paving And Patching Change Order No1
Reflecting an increase of $385,133.00 to the contract with Brothers Asphalt PavingInc.  
(DISTRICTS ALL)
It was moved by  Frerichsseconded by  Kaforskithat this matter be 
recommended to the Board of Trustees for approval.  The motion carried by the 
following vote:
Aye:
Kaforski, Arnold, Blakeslee, Mahal, Kuehl and Frerichs
6 - 
Absent:
John O'Brien
1 - 
080625
South Booster Station Water Transmission Main Change Order No1
Reflecting a time extension of 60 days and an increase of $8,891.94 to the contract with 
Neri Brothers Construction
It was moved by  Frerichsseconded by  Kaforskithat this matter be 
recommended to the Board of Trustees for approval.  The motion carried by the 
following vote:
Aye:
Kaforski, Arnold, Blakeslee, Mahal, Kuehl and Frerichs
6 - 
Absent:
John O'Brien
1 - 
6.0
Other Business
080613
September 12-132008 Storm
Action Items and AAR
Goldsmith:  reviewed memos and reports with the committee members and residents in 
attendance.
1)  Engineering Study
2)  Revise Policy and Staff Response
Will develop some sort of interim solutions to offer to the residents.
Committee and residents discussed the reports and charts.
Will have a recommendation for the next meeting.
Tross:  directed staff to get the committee copies of the "locations of eventsmap.  Add 
this to the previous storm map from last August.  Attach to this a staff recommendation 
and final report of storm event.  Arnold:  graph with blue line of Vista Pond can we see 
these from past storm events for as far back as it goes?  Gorman:  we can provide this 
to the committee.  Tross:  also check the outflow to Gatz Pond.
It was moved by  Kaforskiseconded by  Arnoldthat this matter be recommended 
to the Board of Trustees for approval  The motion carried by the following vote:
Aye:
Kaforski, Arnold, Blakeslee, Mahal, Kuehl and Frerichs
6 - 
Absent:
John O'Brien
1 - 
080629
IGA (Inter-Governmental Agreements)
Gorman:  reviewed the memo with committee.  Tross:  I objected to thisalong with 
several others.  Village Board is looking for a recommendation from this Committee 
regarding this issue.  Committee concurred with staff's recommendations.
It was moved by  Kaforskiseconded by  Mahalthat this matter be recommended 
to the Board of Trustees for approval.  The motion carried by a voice vote
080630
Detention Basin Inspection Results for 2008
It was moved by  Kaforskiseconded by  Frerichsthat this matter be tabled.  The 
motion carried by a voice vote
7.0
Information Only
970045
Project Status Report
980212
Change Order Report
030008
Engineering Monthly Report
8.0
Adjournment
Tross:  introduced Carl Goldsmith, new Public Works Director to the committee.
It was moved by  Frerichsseconded by  Kaforskito adjourn at 10:10 PMThe 
motion carried by a voice vote