Thursday, November 9, 2006
7:00 PM
Village of Lombard
Village Hall
255 East Wilson Ave.
LombardIL  60148
villageoflombard.org
Village Hall Trustees' Conference Room
BOLI Board of Local Improvements
Richard JTrossPresident 
Rick SoderstromVice President
Molly O'TooleJames WHoganJohn O'Brien
Wes AndersonSecretary,  Raymond GSchwabStaff Liaisons
Meeting Minutes
BOLI Board of Local Improvements
Meeting Minutes
November 9, 2006
1.0
Call To Order and Roll Call
The meeting was called to order by President Tross at 7:03 p.m.  Ray Schwab 
requested that BOLI members meet at 6:30 p.minstead of 7:00 p.mfor the December 
meeting.
President Richard J.  TrossVice President Rick SoderstromMolly O'Toole and 
John O'Brien
Present:
James W. Hogan
Absent:
2.0
Public Participation
None
3.0
Approval of Minutes
It was moved by  O'Brienseconded by Vice President Soderstrom,  to approve 
the minutes of October 122006.   The motion carried by a voice vote
4.0
BOLI Consent Agenda
060550
*BOLI has requested that this be tabled until January 42007.
SA 217 Engineering Resource Associates Contract Amendment No5
Reflecting an increase of $257,687.00 for design engineering services. (DISTRICT #4)
Ray Schwab identified the timeline and scope of work for the first four amendments and 
the scope of work covered in amendment #5.   In reviewing the C.I.Pand amendment 
#4Trustees Soderstrom and Tross felt that the $54,078 as approved for amendment #
covered both phases of the sanitary sewer replacement project.  Molly O'Toole 
concurred with Trustees Soderstrom's and Tross's assessment.  BOLI also wished that 
staff had brought forth an amendment concerning Sunset Homes and the watermain fire 
loop to an earlier BOLI sessionas these items have been completed for the last six 
months without formal Board approval of the contract amendment.   The watermain fire 
loop was approved by the Boardhoweverthe formal contract amendment was not 
brought forth by staff.  BOLI expressed their dissatisfaction with staff on this issue and 
wanted to make the Village Manager aware of the situation.   BOLI would like 
Engineering Resource Associates to attend the December BOLI meeting to review 
contract amendment #5.
It was moved by  O'Tooleseconded by  O'Brienthat this matter be tabled.  The 
motion carried by a voice vote
060627
SA 218B Associated Property CounselorsLtdPayout
In the amount of $350.00 for appraisal of 1143 SEdgewood Ave.  (DISTRICT #6)
060626
SA 219 Trine Construction Payout No6
In the amount of $315,883.95 for construction services.  (DISTRICT #6)
060628
SA 219 Testing Service Corporation Payout
In the amount of 803.95 for Geotechnical services.  (DISTRICT #6)
It was moved by Vice President Soderstromseconded by  O'Toole,  to approve 
items 060627060626and 060628.   The motion carried by a voice vote
5.0
Ratification Of Agreements
060382
A request to approve the Petition to Divide Special Assessment 215.  (DISTRICT #3)
060396
QQSpecial Assessment 219 Change Order #(Resolution)
Resolution authorizing Change Order Noto the contract with Trine Construction 
reflecting an increase of $254,039.69 for work associated with Special Assessment 219.  
(DISTRICT #6)
060381
A request to approve payout noto Trine Construction Company in the amount of 
$333,413.63 for construction services related to Special Assessment 219.  (DISTRICT 
#6)
060383
A request to approve payout noto Burns MCDonnell in the amount of $12,038.74 
for resident engineering services related to Special Assessment 219.  (DISTRICT #6)
060380
A request to approve a payout to Testing Services Corporation in the amount of 
$7,948.90 for geotechnical services related to Special Assessment 219.  (DISTRICT #6)
It was moved by  O'Tooleseconded by  O'Brien,  to approve items 060382
060396060381060383and 060380.   The motion carried by a voice vote
6.0
Unfinished Business
7.0
New Business
8.0
Other Business
Trustee Soderstrom reviewed issues regarding Special Assessment 218(Edgewood 
Ave.).  Due to the project's minimal improvement to the area's stormwaterand 
easement issuesthe Village Board will abandon Special Assessment 218B.  Given the 
parameters of the projectit was not financially or physically possible to achieve the 
Village's objectives.  Trustee Soderstrom made a motion for BOLI to formally abandon 
Special Assessment 218B.
It was moved by Vice President Soderstromseconded by  O'Toole,  to approve 
abandoning Special Assessment 218(Edgewood Ave.)   The motion carried by a 
voice vote
9.0
Information
10.0
Adjournment
It was moved by Vice President Soderstromseconded by  O'Tooleto adjourn the 
meeting at 8:22 p.m.   The motion carried by a voice vote