Tuesday, August 10, 2004
7:00 PM
Village of Lombard
Village Hall
255 East Wilson Ave.
Lombard, IL  60148
villageoflombard.org
Village Hall Community Room
Public Works Committee
Trustee Steven DSebby, Chairperson
Trustee Rick Soderstrom Vice Chairperson
John Kaforski, Rick Mahal, David Arnold,  Art Frerichs,
Ken Blakeslee and Dan Mahal
Staff LiaisonsWes Anderson and David Dratnol
Meeting Minutes
Public Works Committee
Meeting Minutes
August 10, 2004
1.0
Call to Order and Roll Call
The meeting was called to order by Chairperson Sebby at 7:04 p.m.
Chairperson Trustee Steven DSebby, Rick Mahal, John Kaforski, David 
Arnold, Ken Blakeslee, Dan Mahal and Art Frerichs
Present:
Vice Chairperson Trustee Rick Soderstrom
Absent:
2.0
Public Participation
None
3.0
Approval of Minutes
It was moved by  Blakeslee, seconded by  Frerichs, to approve the minutes of the 
May 112004, meeting.   The motion carried by a voice vote
4.0
Unfinished Business
Dratnol informed the committee that the full package for the Street Lighting 
Specifications will be on the next agenda.
 
Sebby asked about the Sidewalk Program.  Dratnol reviewed that additional funding was 
approved by the Board of Trustees.  The additional funding allows the trip hazard 
program to be caught up to June.  Once the program is caught up, Public Works will 
evaluate where it stands budget-wise.  In the Fall sidewalk program will be on the 
agenda.  Sebby pointed out that if someone wants to participate financially, it would be a 
nice option to have funds available for that.  
 
Sebby asked for an update on the whitetopping.  Dratnol responded that Public Works 
charted out any distress on each piece.  We will bring information to the next meeting.  
Engineering will do that as we survey about every months.  Arnold pointed out that we 
just did surface treatment on the asphalt portion, that adds to the cost.
5.0
New Business
040346
Y.   Special Assessment 218 Change Order #(Resolution)
 Resolution authorizing Change Order #to the contract with R.WDunteman Company 
reflecting an increase of $18,253.27 for additional work associated with Special 
Assessment 218.  (DISTRICT #6)
It was moved by  Kaforski, seconded by  Blakeslee, that this matter be 
recommended to the Board of Trustees for approvalThe motion carried by a 
voice vote
Enactment NoResolution 35-05
040356
Z.   Lombard Lagoons and Veterans Pond Change Order #(Resolution)
 Resolution authorizing Change Order #to the contract with R.WDunteman Company 
reflecting an increase of $13,640.80 for work associated with the Lombard Lagoon & 
Veterans Pond Project.  (DISTRICT #4)
It was moved by  Frerichs, seconded by  Mahal, that this matter be recommended 
to the Board of Trustees for approvalThe motion carried by a voice vote
Enactment NoResolution 36-05
040360
AA.  Lombard Hills East (Phase VReconstruction Change Order #(Resolution)
 Resolution authorizing Change Order #to the contract with R.WDunteman Company 
reflecting an increase of $66,818.20 for work associated with the Lombard Hills East, 
Phase Project.  (DISTRICT #4)
It was moved by  Arnold, seconded by  Mahal, that this matter be recommended 
to the Board of Trustees for approvalThe motion carried by a voice vote
Enactment NoResolution 37-05
040345
X.   Hammerschmidt Parking Lot Change Order #(Resolution)
 Resolution authorizing Change Order #to the contract with the R.WDunteman 
Company reflecting a decrease of $58,606.72 reflecting as-measured field quantities for 
the Hammerschmidt Parking Lot Project. (DISTRICT #4)
It was moved by  Mahal, seconded by  Blakeslee, that this matter be 
recommended to the Board of Trustees for approvalThe motion carried by a 
voice vote
Enactment NoResolution 34-05
6.0
Other Business
Dratnol gave an update on several construction projects.
 
Charlotte (Olde Town East) - waiting for ComEd to move a pole.  
 
Main Street Precon with IDOT is scheduled.  Construction should start late August.  St
Charles to Rt64 is a separate project.
 
Streetscape & grind & overlay on ???
 
Highland Avenue is switching from stage to on 8/27.  It's still on track for 11/
completion.
 
Rt64-Substantial completion mid-late September.  
 
Arnold asked what the policy is for how we schedule the street sweeping.  Burg 
responded that we go through the town systematically.  We may concentrate more on 
commercial.  Arnold suggested that the residential sweeping be done on the day after 
garbage pick up.  Dratnol explained that because of the large area of garbage pick up 
they couldn't get it all.  
 
Kaforski stated that there are skid marks at Hammerschmidt/Harrison.  He also thought 
that the garbage trucks may be pulling up the crack sealing.
7.0
Information Only
970045
Concoord 
970046
Restoration List 
970153
Construction Barricade Reports (light deficiencies
980212
Change Order Report 
030008
Engineering Monthly Report 
8.0
Adjournment
It was moved by  Mahal, seconded by  Mahal, to adjourn the meeting at 7:55 p.m.   
The motion carried by a voice vote