Tuesday, December 8, 1998
7:30 PM
Village of Lombard
Village Hall
255 East Wilson Ave.
Lombard, IL  60148
villageoflombard.org
Village Hall Community Room
Public Works Committee
Trustee Steven DSebby, Chairperson
Trustee Rick Soderstrom Vice Chairperson
John Kaforski, Rick Mahal, David Arnold,  Art Frerichs,
Ken Blakeslee and Dan Mahal
Staff LiaisonsWes Anderson and David Dratnol
Meeting Minutes
Public Works Committee
Meeting Minutes
December 8, 1998
1.0
Call to Order and Roll Call
Trustee Ralph Borgatell, Trustee John DeFalco, Gordon Hallbeck, John 
Kaforski, Committee Member Trustee Joan DeStephano, John Meyer, Stephen 
Preins and David Arnold
Present:
2.0
Public Participation
Graham PHart    Lincoln Court    Lombard, IL
Laura McGovern, P.E.    Burns and McDonnell
3.0
Approval of Minutes
It was moved by  Hallbeck, seconded by  Preins, to approveThe motion carried 
by a voice vote
4.0
Old Business
980675
MrLichter informed committee there have been several changes since the last meeting 
with PW staff.  The Village Board directed they would like to see all of the unimproved 
street projects within next years.  A number of projects will be pushed back a year or 
two but are still trying to bring them back up.  Mr Lichter reviewed his memo from 
December 4th.  There are a few projects that are not moved back up:  StCharles from 
Martha to 53 by Ridge Ave.;  reduced concrete rehabby about 3million in order to have 
necessary funds; there is not enough time to start SA213/214 next year, are proposing 
SA213/214 be done in one construction season.Due to the size of this project, would 
start underground early in 2000.  What was to be special assessments will now be one 
and completed in 2000.  Because it will now be one project, it will be renumbered as 
SA213.  Next change SA216, then SA217 will be moved up from 2003 to 2002, and 
completed as SA216.  SA218/219 will be combined in to one project...rather than 
completed as projects, and renumbered as SA217 to be done in 2003.  SA220 will be 
renumbered as SA218 to be done in 2004.  This would allow completion of construction 
in years.  In Traffic Engineering and Control:  moved opticom up.  Traffic signal 
Highland and Majestic to 2001.  Hammershmidt detention facility has moved to next 
fiscal year.  We are talking to the school district about combined funding; this is very 
preliminary.  The biggest change is with the Special Assessments.
GH:  with regards to SA214...how much work was done last summer at Harrison and 
Rte53?  BL:  we repaired that with our own crewsSR:  we added some stone and did 
some surface treatment.  SP:  it was closed for 10 days.  JK:  it was pretty bad over 
there; this was just a temporary solution.  SR:  our work was extremely cheap over 
there(under $20,000).  JDS:  Harrison from that point east was repaired in 1989; a 
definite bonus.  GH:  in maintaining an unimproved street in the past we never spent that 
amount of money.  BL:  we did the same thing on 20th and 17th.  GH:  if we combine 
Ahrens in to one project, where are all of the residents going to park?  DD:  will look at 
that as part of the project, and take in to consideration.  GH:  they will be hurting for 
parking spots.  JK:  possibly use Veterans hall for parking.  GH:  needs consideration.  
RB:  aren't there some 1-block areas that are not improved?  Can we get these in?  
BL:  we would need engineering; would need to be Special Assessments.  We don't 
want to push back projects that are already scheduled.  RB:  what we have done is 
basically picked up the bigger areas.  BL:  do have Charles Lane, which is smaller.  GH:  
could we, for January, get a map with the 1-block unimproved areas marked on it; 
also, what is on the CIP(highlighted)?  BL:  we can do an update of the last map we 
gave you.  We will put that together for you.  What will be the new SA213  is a little piece 
of Troy Lane and Glenview.  Another possibility with SA214 is Charles Lane is not too 
far from Harrison; possibly could be an add on.    SP:  asphalt maintenance numbers are 
not going up, crack sealing, surface treatment are not going up? We should question 
this.  BL:  numbers were given to us by PW.  SP:  as more and more asphalt is laid, it 
will need more treatment.  BL:  this is the number I was given; I will look at it.  JM:  
pushed back Wilson?  BL:  that was one that the Village Board felt was fine.  On Page 2
have put in funds for Grove between Main and Charlotte..took a look at water and sewer 
to serve street and new condos that are being constructed.  Have pushed that project up 
to next year.  On Page 3:  Washington from Martha to Addison moved from 2007 to 
2008.  Will continue to reevaluate this.  JDS:  How bad is Ridge Ave.(Page 4)  SR:  
Ridge north of North Aveis in an Industrial area.  Primary concern out there is the 
"Ridge Dip"; did some utility work there (water and sewer).  Should be fine for now, have 
corrected utilities.  BL:  On Page 5:  Butterfield Frontage Rd....we finally have an 
agreement with NIGAS to loop water main around there; trying to move that up.  GH:  
part of this is State and part is Lombard's.  SR:  it is State right-of-way.  GH:  will they 
dictate to us what to do?  Let's check this out.
980737
Graham Hart, resident from Lincoln Court, in attendance.  SR:  introduced MrHart.  
Background:  MrHart applied through the grant program.  He installed an overhead 
sewer in 1987.  Committee looked at it and decided that it was too far back to be 
considered in this program.   MrHart has supplied another narrative for consideration.  
He has proposed to install a new modified inside the wall drain tile system tied to a new 
sump pump pit to discharge onto the lawn (proposal attached). 
SP:  are the existing drain tiles going to the sewer the problem?  You would saw-cut the 
drain all of the way around?  MrHart:  correct.  GH:  this is not sewage, but excess 
drain waterMr Hart:  correct.  GH:  is that a combined system out there?  SR:  yes.  
GH:  is his line coming in at the top of the 108?  SR:  the whole block is that way.  We 
have not televised that line yet, correct Angela?  AP:  yes.  The problem is they are 
coming in low.  Park and Hickory is this way also.  JK:  this is ground water coming in 
the walls?  MrHart:  it is coming in the keyhole.  Have had the walls water proofed, I 
mean the key way.  JDS:  is clear brown water?  Mr Hart:  correct.  SP:  this doesn't fit in 
to our program, but I'm for giving him the money to help him out.  GH:  I have no 
problem either, with the understanding that this is a one time deal.  JK:  my dealings with 
the plugs that you are having installed, the plugs only last a few years, and they will 
have to be redone.  I don't have a problem either with this as a one shot deal, as Gordon 
statedBL:  does this require the policy to be adjusted?  SP:  what did Tom say?  SR:  
Tom is in agreement.  In the policy there is a phrase that talks about the "system".   We 
could take this as a case or a problem that falls within this area.  In future proposals, we 
would hope to approve these also.  SP:  if we see a lot of these come across, we may 
have to adjust language in the policy to fit this type of situation.  JK:  he did install an 
overhead sewer system.  SR:  we are comfortable approving this as an administrative 
decision if the PW Committee concurs with staff that this is acceptable under the 
overhead sewer program.  MrHart:  thank-you to the PW Committee and PW staff for 
all of their help.
5.0
New Business
980717
Laura McGovern in attendance for presentation.  AP:  this is in regards to controls for 
systems and Lift station/pump station.  We decided to combine field study for both 
projects since they were going to be handled by the same Engineering firm.  I have 
supplied you with the reports.  
Laura McGovern gave overhead presentation, which summarizes large amount of 
documents passed out.
 
LM:  the PLC manufacturer we recommend is Allen Bradley.  JM:  can PW staff program 
this?  LM:  Jim Izzi has taken classes and could probably operate.  AP:  would probably 
hire a system integrator to put us up on line and then train staff.  Initial integration would 
take about 2000 hours.  
LM:  in regards to communications we eliminated cable tv and MAS radios do not have 
signals available.  A dedicated telephone is great.   There is something in the south end 
of Lombard that affected the Spread Spectrum radios.  Fiber Optic cable is very 
expensive, around million.  Would recommend dedicated telephone at about $750.00 
per site, per year.  JK:  can we apply for a dedicated frequency?  LM:  there are none 
available to apply for.  JK:  I thought the government just released a whole new group?  
LM:  none of those frequencies fit this spectrum.  Would also recommend going with 
Itellutions (DMACS), Window NT, Alarm Dialer Card connected locally to PLC, connect 
with Microsoft Office and Autodialer.  
 
Recommended System of Architecture:
JDS:  regarding Phase I, what is the impact of Y2K on this if schedule slips?  LM:  could 
have a significant impact.  JDS:  Phase II will not be effected by Y2K problems?  LM:  
there will be no affect.  AP:  no processors out there in Phase II.  We do have a backup 
which would mean switching to manual.  
 
AP:  funds are available for SCADA and also some other projects that we have put on 
the shelf...we have $150,000 available that will be carried over in this budgetFor water 
systems and engineering we will need about $640,000 in the CIP.  Funding for lift 
stations comes primarily from lift station improvements in the CIP (Page 7)  BL:  as lift 
stations are replaced, control systems will be put in place.  Talked about setting aside 
1/million  for SCADA and lift station improvements/replacements out of water funds.  
There should be sufficient funds to take care of this.  SP:  looks like we are about 
$250,000 short.  BL:  funding is available in different sources; we can spell out a little 
clearer if necessary.  AP:  we broke down in a spread sheet the funding that we have, 
what we need, etc.  SPwe need to spell out specifically what is available for this.
LM:  broken down into colors:  red:  critical before 2000; bluecomplete by 1999;  green 
is Phase II.
JM:  is it feasible to escalate any or all of this if necessary?  LM:  if funding was there, it 
would be great.  What we have come up with certainly addresses the problem 
sufficiently.  RB:  How many years of "trouble free yearsdo we have?  LM:  the base is 
34 years.  We did an installation for Bloomingdale in 1992, and haven't touched the 
system since.  AP:  we have used this software since 1980 original installation.  LM:  
nice things about PLC's is that they never fail completely.  AP:  key thing will be our 
alarm capabilities/now we are notified by police or residents; a very timely process.  
Normally flooding occurs.  
Lift Station/Pump Station Master Plan:  Laura McGovern passed out page report for 
reference.  
LM:  Sanitary Basin Analyses:  need to install safety nets in hatches.  Elizabeth/Morris 
Lift Station is marginal in capacity, should have pumps.  
Immediate Repairs/Recommendations:  pull meters up (done in house).  Village has 
completed these.
LM:  Prioritization:  #1.  Yorktown Lift Stationreplace at $240,000.  
Regarding BUDGET, Stations Recommended for Replacement:
The top stations are in serious trouble.  Would suggest putting Glen Oak ahead of 
Finley due to structural problems.  AP:  Vista Pond originally on for repairs/reevaluated 
and now needs to be replaced
LMPriority Improvements:
A.  absolutely need to be done.
B.  strongly suggested.
C.  make life easier and more convenient.
All itemized in report you should receive by the end of the week.
GH:  as we make improvements, should we go to 1-different types of pumps instead of 
7-we have now?  LM:  need to try to get everything consistent.  JMis staff in 
concurrence with time on this?  If funding is only issue, possibly we should escalate 
this?  BL:  money is the reason we have laid this out this way; there is a lot of debt with 
the street issues.   We can look at it a little further before the 3rd draft of the CIP.  JK:  
the benefit of this is that it is able to be phased in.  JM:  we don't want to speed up 
something that is not necessary, but we don't want to end up in trouble either.  BL:  am 
more concerned about structures at this point.  Priority lift station repairs should be 
complete in a few years; the controls have to work.  GH:  how much is it costing us in 
man hours, etc., to check these stations?  JM:  money should not be the driving issue 
with this project.
Committee thanked Laura McGovern for an excellent presentation.
6.0
Change Orders
Stan Rickard passed out a sheet with all change orders from this year.
980720
A RESOLUTION AUTHORIZING A CHANGE ORDER
INVOLVING AN DECREASE IN THE DOLLAR AMOUNT OF 
THE CONTRACT OF $10,000 OR MORE 
It was moved by  Hallbeck, seconded by Trustee DeStephano, that this matter be 
recommended to the Board of Trustees for approvalThe motion carried by a 
voice vote
Enactment NoResolution 88-99 Con
980721
Should have been written differently with a better explanation.
It was moved by  Hallbeck, seconded by  Preins, that this matter be recommended 
to the Board of Trustees for approvalThe motion carried by a voice vote
Enactment NoResolution 97-99 Civ
980733
A RESOLUTION AUTHORIZING A CHANGE ORDER
INVOLVING A DECREASE IN THE DOLLAR AMOUNT OF  THE CONTRACT OF $10,000 OR 
MORE
It was moved by  Meyer, seconded by  Kaforski, that this matter be recommended 
to the Board of Trustees for approvalThe motion carried by a voice vote
Enactment NoResolution 89-99 Fin
980734
A RESOLUTION AUTHORIZING A CHANGE ORDER
INVOLVING A DECREASE IN THE DOLLAR AMOUNT OF 
THE CONTRACT OF $10,000 OR MORE 
It was moved by  Preins, seconded by  Meyer, that this matter be recommended to 
the Board of Trustees for approvalThe motion carried by a voice vote
Enactment NoResolution 90-99 Lom
980735
A RESOLUTION AUTHORIZING A CHANGE ORDER
INVOLVING A DECREASE IN THE DOLLAR AMOUNT OF 
THE CONTRACT OF $10,000 OR MORE 
It was moved by  Preins, seconded by  Kaforski, that this matter be recommended 
to the Board of Trustees for approvalThe motion carried by a voice vote
Enactment NoResolution  91-99 Ol
980736
A RESOLUTION AUTHORIZING A CHANGE ORDER
INVOLVING AN INCREASE IN THE DOLLAR AMOUNT OF  THE CONTRACT OF $10,000 OR 
MORE
It was moved by  Preins, seconded by  Hallbeck, that this matter be recommended 
to the Board of Trustees for approvalThe motion carried by a voice vote
Enactment NoResolution 92-99 SA
7.0
Pending Change Orders
8.0
Other Business
Committee addressed the possibility of pictures, etcdocumenting major change orders 
(as an example:  pictures of tree that was found at Maple StLot that caused increase in 
amount of this project).  Dave Dratnol responded:  A lot of times this would be very 
difficult.  A tree, yes that is possible.  But other situations, such as poor soil, not 
possible.  Most of the time, decisions need to be made when you open up the ground.  
Also, a photo is not necessarily going to tell you or show you what the problem is/was.  
Inspector tries to make a report/don't always have the luxury of "time".  SP:  when there 
is a structure that poses a problem, would like to have a photo or video if possible.  JDS:  
Olde Town underground creek video with rushing water was a great presentation that 
showed us the problem out there.
9.0
Information Only
970045
Concoord 
970046
Restoration List 
970047
Procurement Schedule 
970153
Construction Barricade Reports (light deficiencies
980212
Change Order Report 
980528
Overhead Sewer Grant Program-List of Applicants 
10.0
Adjournment
It was moved by  Preins, seconded by  Kaforski, to adjourn the meeting at 10:09 
pmThe motion carried by a voice vote