Public Works Committee
Village of Lombard
Village Hall
255 East Wilson Ave.
LombardIL  60148
villageoflombard.org
Meeting Minutes
Trustee Richard JTross-Chairperson
Trustee Jack O"BrienAlternate Chairperson
John KaforskiArthur KuehlDavid Arnold,  Art Frerichs,
Ken Blakeslee and Dan Mahal
Staff LiaisonsWes Anderson and David Dratnol
7:00 PM
Village Hall Community Room
Tuesday, July 11, 2006
1.0
Call to Order and Roll Call
Art Frerichs arrived at 7:12 PM.
Richard J.  TrossJohn KaforskiDavid ArnoldKen BlakesleeDan Mahal
Arthur Kuehl and Art Frerichs
Present:
2.0
Public Participation
Approval of Minutes
3.0
It was moved by  Kaforskiseconded by  Arnoldto approve.  The motion carried 
by a voice vote
4.0
Unfinished Business
5.0
New Business
060353
FY 2005 Sewer Televising Program Final Balancing Change Order No
(Resolution)
Resolution authorizing final balancing Change Order Noto the contract with A-
Underground reflecting a decrease of $18,756.91 representing the final as-measured 
quantities for the 2005 Sewer Televising Program
It was moved by  Blakesleeseconded by  Arnoldthat this matter be 
recommended to the Board of Trustees for approval.  The motion carried by a 
voice vote
060354
FY 2006 Underground Structure Program Final Balancing Change Order No
(Resolution)
Resolution authorizing final balancing Change Order Noto the contract with A Lamp 
Concrete Construction reflecting a decrease of $6,245.12 representing the final 
as-measured quantities for FY06 Underground Structures Program.  
It was moved by  Kaforskiseconded by  Arnoldthat this matter be recommended 
to the Board of Trustees for approval.  The motion carried by a voice vote
060355
FY 2005 Dust Control Program Final Balancing Change Order No(Resolution)
Resolution authorizing final balancing Change Order Noto the contract with CAM
LLC reflecting a decrease of $10,200 representing the final as-measured quantities for 
the FY05 Dust Control Program.  
It was moved by  Mahalseconded by  Kuehlthat this matter be recommended to 
the Board of Trustees for approval.  The motion carried by a voice vote
060356
FY 2006 Asphalt Paving and Patching Program Final Balancing Change Order No
(Resolution)
Resolution authorizing final balancing Change Order Noto the contract with R.W
Dunteman reflecting a decrease of $33,559.73 representing final asmeasured 
quantities for the FY2006 Asphalt Paving and Patching Program.  
It was moved by  Blakesleeseconded by  Kuehlthat this matter be 
recommended to the Board of Trustees for approval.  The motion carried by a 
voice vote
060369
2004 Yorktown Watermain Change Order #(Resolution)
Resolution authorizing final balancing Change Order Noto the contract with Trine 
Construction reflecting an increase of $53,923.66 for work associated with the Yorktown 
WatermainPhase project.  (DISTRICT #3)
Dratnol reviewed change order with committee members.  Tross:  this is beginning to 
look like a big amount of money.  Dratnol:  this contract has been nothing but problems
contaminated soilComEd issuesetc.  Kaforski:  as I look at thiswe do not even know 
where some of our own things are.  Dratnol:  I agreebut a lot of times there are reasons 
for this.  Kaforski:  there should be records of these utilities somewhere.  Dratnol:  a lot 
of this goes back to when the mall was built in the 60's.  We have to count on utilities to 
give us good information.  We are starting to do exploratory digs because of what has 
happened with this contract.  Tross:  how much of this is a Yorktown infrastructure 
issue(we accepted their as-builts)  Dratnol:  where you see change orders associated 
with serviceswe could not trace any of them.  We were using the best technology that 
was available to us.  Mahal:  who is going to control and keep records of the new work 
that is being done (convention centerconvenience center)?  Dratnol:  we keep much 
better records now (GISetc.)  Services are still really hard to keep track of.  We are 
improving the record retention.
It was moved by  Arnoldseconded by  Mahalthat this matter be recommended 
to the Board of Trustees for approval.  The motion carried by the following vote:
Aye:
Kaforski, Arnold, Blakeslee, Mahal, Kuehl and Frerichs
6 - 
6.0
Other Business
Tross asked Dratnol to review SA219.  Dratnol:  number for change order looks like it is 
going to come in around $200,000.00.  New watermain on east side of Ahrens.  Plans 
are at EPA for approval.  Once we get thatwe will bring the change order in.
7.0
Information Only
970045
Project Status Report
980212
Change Order Report
030008
Engineering Monthly Report
060336
Railroad Right-of-Way Issues between Grace Westmore
Dratnol:  proposals for landscaping work are $2000-$7000.  Tross:  received e-mail from 
Bill Muellerspoke with Joyce Stupegia  from Villa Park.  President's Committee 9/at 
9:00 AM.  Tross read memo to committee.  Dratnol:  T&S asked PWC to look at this.
8.0
Adjournment
Adjourned at 7:43 PM.
It was moved by  Blakesleeseconded by  Mahalto adjourn.  The motion carried 
by a voice vote