Title:
|
Approval of Change Order #2, Carriage House Addition
Resolution approving Change Order #2 in the amount $11,684.52 to the contract with Action 1 Construction due to a request for changes to the carriage house plans that were made by the building department to the plans after the project had been bid. (DISTRICT #1)
|